Press with a quick-change die with fasteners, a large stopwatch and a poka-yoke device with an approved part

Quick answer: Shigeo Shingo was a Japanese industrial engineer, a consultant to Toyota and other companies, associated with two core lean techniques: quick changeover (SMED) and poka-yoke, a device that stops an error before it becomes a defect. He complemented the Toyota Production System with engineering methods.

Advertisement

Who was Shigeo Shingo

Shigeo Shingo (1909 to 1990) was a Japanese industrial engineer who worked as a productivity and quality consultant, including for Toyota. His name became tied to SMED and poka-yoke, two techniques now present in factories all over the world.

He wrote technical books that spread these methods outside Japan, among them A Revolution in Manufacturing: The SMED System and Zero Quality Control: Source Inspection and the Poka-yoke System, published in English in the 1980s. There is also an operational excellence award in the United States that carries his name.

Check dates and titles in the book editions before citing them in formal work. Shingo is usually cited alongside Taiichi Ohno: Ohno was the architect of Toyota's production system, and Shingo contributed engineering techniques that made the system possible in practice.

SMED: changing tooling in minutes

SMED stands for Single Minute Exchange of Die, a die change in single-digit minutes. Shingo's central idea was to distinguish two types of activity in a tooling changeover (setup):

Many changeovers take long because external activities are done with the machine stopped. Moving everything possible to the external side reduces machine downtime, without buying new equipment. This allows smaller batches, more variety and less inventory, which fits with just-in-time.

The best-known account is that of a large Toyota press, where the changeover is said to have dropped from hours to a few minutes over some months of work. Exact numbers vary by source. What matters is the logic of the method, which works on presses, injection molding machines, packaging machines and even administrative activities.

The SMED steps

StepWhat to doExample
0. Study the current situationTime and film the changeover, without separating anythingA 90-minute changeover, with everything mixed together
1. Separate internal and externalList each task and classify it30 minutes were external tasks done with the machine stopped
2. Convert internal to externalPrepare beforehand, preheat, standardize heights and fixturesPreheat the die outside the machine: 15 minutes less
3. Improve every aspectSimplify clamping, eliminate adjustments, run tasks in parallelQuarter-turn fasteners: 15 minutes less

Worked example. A press does two changeovers per 8-hour shift, and each one takes 90 minutes. The gain from each step:

StepReductionMachine downtime per changeover
Starting point90 min
Separate and move the external work out of the stop− 30 min60 min
Convert internal to external (preheating)− 15 min45 min
Simplify clamping− 15 min30 min

The changeover fell from 90 to 30 minutes, a reduction of 60 minutes, or about 67%. With two changeovers per shift, the machine goes from being stopped 2 × 90 = 180 minutes to 2 × 30 = 60 minutes. Gain: 120 minutes per shift, or 2 hours of capacity returned to production, with no machine investment. The savings are bigger if changeover time is a bottleneck, as OEE usually shows in availability.

SMED techniques in practice

TechniqueWhat changesExample
Quick-release fastenersReplaces long bolts with quarter-turn fasteners, clamps or latchesClamp the die with 4 latches instead of 12 bolts
Guide and centering pinsEliminates position adjustment when mounting the toolA die that always seats in the same position
Standardized heights and dimensionsAvoids shims and adjustments between different toolsAll dies with the same shut height
Parallel operationsTwo people work at the same time, on opposite sides of the machineOne loosens while the other prepares the next tool
Changeover cart or kitEverything the changeover needs in a single organized cartWrenches, shims and parts gathered and labeled
Eliminating adjustmentsReplaces trial-and-error adjustment with fixed references or scalesA scale with marks for each product

Start with the cheapest techniques, such as organization and standardization, which depend on method and discipline rather than on buying equipment. Gains that require more investment are left for later, when the result of the first actions justifies them.

Poka-yoke and source inspection

Shingo's second well-known contribution is poka-yoke, Japanese for "avoiding inadvertent errors". The most-told story says he replaced the earlier term, considered offensive, with one that does not blame the person: human error is natural and the system has to prevent it.

Shingo distinguished three types of inspection:

Poka-yoke devices work through three classic methods: contact (the shape of the part only allows it to fit one way), fixed value (counts the number of cycles or parts and alerts if one is missing) and motion sequence (checks whether the steps were done in order). For each method, there is a control function (stops the process from continuing) or a warning function (gives notice). Control is stronger.

The tightening counter that stops the part from advancing without all four screws is an example of the fixed-value method. See the case in the PFMEA article. The principle connects with jidoka: the process stops, and the problem is solved at the source.

Advertisement

Poka-yoke examples by method

MethodHow it worksFactory example
ContactThe shape or size of the part only allows the correct fitConnector with a position key, a fixture that only accepts the part in the right position
Fixed valueCounts the number of movements, parts or cycles and alerts if it is wrongTightening counter: releases the part only with all 4 screws
Motion sequenceChecks whether the steps were done in the right orderSensors that confirm the assembly order of the parts
Presence sensorDetects the absence or excess of a part before moving onSensor that confirms the washer before tightening
Parameter controlStops the cycle if the variable leaves the rangePress that does not cycle if the pressure is outside the limit

The question that guides the choice is: what is the simplest way to make the error impossible? If it cannot be prevented, warn immediately, at the point where the error happens. Simple, cheap devices made with the team last longer than sophisticated solutions.

The ideas behind the techniques

How to apply it today

SMED, in five steps:

  1. Choose the machine with the most changeovers or the one that limits the flow.
  2. Film a complete changeover and list all the tasks, with times.
  3. Classify each task as internal or external and move what you can out of the stop.
  4. Standardize tools, heights and fasteners, and create an organized changeover kit (see 5S).
  5. Record the new standard, train the shifts and measure again.

Poka-yoke, in four steps:

  1. List the most frequent defects, with a Pareto chart.
  2. Find out at which step the error originates.
  3. Design a simple device: guide, sensor, counter, fixture.
  4. Test it, and check that the error no longer occurs.

Improvement is continuous: each gain becomes the new standard of kaizen.

Common mistakes when applying Shingo's ideas

Frequently asked questions

Who was Shigeo Shingo?

He was a Japanese industrial engineer (1909 to 1990), a consultant to Toyota and other companies, associated with SMED (quick changeover) and poka-yoke (mistake-proofing devices).

What is SMED?

It is a method for reducing tooling changeover (setup) time. The idea is to separate what can only be done with the machine stopped (internal) from what can be done while it runs (external), move as much as possible to the external side, then simplify what is left.

What does poka-yoke mean?

It is a Japanese term for avoiding inadvertent errors. It describes devices and methods that prevent errors or warn about them before they become defects.

What is the difference between Shingo and Ohno?

Ohno was the chief architect of the Toyota Production System. Shingo worked as a consultant and contributed engineering techniques such as SMED and source inspection.

What are the SMED steps?

Study the current situation, separate internal and external activities, convert internal to external and improve every aspect of the changeover.

What is the Shingo Prize?

It is an operational excellence award in the United States that carries the name of Shigeo Shingo. Check the institute's official website for the criteria and the current status.

Sources

  1. SHINGO, S. A Revolution in Manufacturing: The SMED System. Portland: Productivity Press, 1985.
  2. SHINGO, S. Zero Quality Control: Source Inspection and the Poka-yoke System. Portland: Productivity Press, 1986.
  3. LIKER, J. K. The Toyota Way. New York: McGraw-Hill, 2004.
  4. Lean Enterprise Institute, general reference on lean: https://www.lean.org/

This article is a teaching guide. The numerical examples are fictional and only show how the calculation works; use your own company's data and criteria. For questions about standards or manuals, consult the official document. See also the learning paths and the A–Z glossary.

Want to reduce losses on your line?

Download the free Metrics That Matter e-book, with OEE, takt time and visual management.

Download the e-book
Advertisement
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.