
Quick answer: WIP (work in process, also called work in progress) is all the material that has entered production and has not yet become a finished product: parts waiting, being processed or sitting between operations. By Little's Law, WIP = throughput × lead time. Reducing WIP shortens the production lead time and frees up capital, without having to produce faster.
What is WIP
WIP stands for work in process (or work in progress), also called in-process inventory. It is everything that has left the raw material stockroom, entered production and has not yet reached finished goods inventory.
The three main types of manufacturing inventory help locate the WIP:
| Type | What it is | Where it sits |
|---|---|---|
| Raw material | Purchased material, not yet used | Incoming stockroom |
| Work in process (WIP) | Material being transformed or waiting for the next operation | On the shop floor, between machines, on pallets and carts |
| Finished goods | Product ready for delivery | Shipping |
In accounting, WIP usually appears as goods in process inventory. In lean management, it gets special attention because it is the inventory that hurts flow the most and the one you see the least.
Why WIP matters
- Tied-up capital: each part in process has already received material, labor and energy, but has not yet generated revenue.
- Longer lead time: the more parts in the queue, the longer each one waits. See lead time.
- Hidden defects: a problem in one operation only shows up when the part reaches the next one. With a lot of WIP, you find out after producing hundreds of bad parts.
- Space and handling: inventory takes up room, requires transport and causes loss and damage.
- Less flexibility: changing priorities is hard with a huge queue in front.
In lean language, excess WIP is the visible form of the wastes of inventory and waiting, and it usually hides flow problems, long setups and stoppages. It is among the wastes of lean.
How to calculate WIP and Little's Law
There are two ways to measure it. The first is direct counting: at each hour or shift, add up the parts or batches waiting and being processed at each point of the flow. The second uses Little's Law, a mathematical relationship between three quantities of a stable process:
WIP = throughput × lead time
Lead time = WIP ÷ throughput
Throughput is the quantity that leaves the process per unit of time, and lead time is the time a part takes from entry to exit. The law holds for roughly stable processes, and was proved by John D. C. Little, in 1961, in the context of queues.
The practical consequence is strong: if throughput does not change, reducing WIP reduces lead time in the same proportion.
Worked example: from 480 to 240 parts
A teaching example. A line produces 120 parts per hour and, in one count, there were 480 parts in process, distributed like this:
| Step | WIP before (parts) | WIP after (parts) |
|---|---|---|
| Cutting | 150 | 60 |
| Machining | 190 | 80 |
| Assembly | 90 | 60 |
| Painting | 50 | 40 |
| Total | 480 | 240 |
Calculations using Little's Law:
| Item | Before | After |
|---|---|---|
| Lead time (WIP ÷ throughput) | 480 ÷ 120 = 4 hours | 240 ÷ 120 = 2 hours |
| WIP value (average cost of $35 per part) | 480 × 35 = $16,800 | 240 × 35 = $8,400 |
| Production cost per day (120 × 8 h × $35) | $33,600 | $33,600 |
| WIP coverage in days of production | 16,800 ÷ 33,600 = 0.5 day | 8,400 ÷ 33,600 = 0.25 day |
Keeping the same throughput of 120 parts per hour, lead time fell from 4 to 2 hours, and the capital tied up in the process fell from $16,800 to $8,400, a release of $8,400. To reach a 2-hour lead time at 120 parts per hour, the WIP limit is 120 × 2 = 240 parts. This number becomes the rule that guides the flow.
Note: throughput is only maintained if the bottleneck is well supplied. Reducing WIP without fixing stoppages and variation can, on the contrary, reduce output. That is why you reduce gradually.
Why WIP grows
| Cause | How it creates WIP | Symptom on the shop floor |
|---|---|---|
| Large batches | Each part waits for the whole batch to be processed | Full pallets in front of the machines |
| Long setups | To make up for the slow changeover, you produce in large batches | Few changeovers per day, batches that last days |
| Poorly supplied or unstable bottleneck | Upstream steps produce beyond the bottleneck's capacity | Queue growing before the bottleneck, empty after it |
| Stoppages and breakdowns | When one step stops, the others keep going and pile up | Inventory appears and disappears with the stoppages |
| Early scheduling | Orders released beyond what the flow can handle | Factory full of open orders |
| Rework and parts under review | Parts outside the normal flow wait for a decision | A "quarantine" area that is always full |
7 ways to reduce WIP
- Limit WIP per step. Define the maximum allowed between operations. When the limit is reached, the previous step stops. This is the principle of kanban.
- Reduce batch sizes. Smaller batches cut the wait per batch. It depends on faster setups (see SMED).
- Balance the flow to takt time. Steps with different times create queues. Calculate takt time and level the loads.
- Create continuous or one-piece flow where it makes sense, bringing the operations closer together.
- Eliminate the stoppages and breakdowns that make the queue build up, with maintenance and OEE.
- Level production. Demand peaks create WIP peaks. See heijunka.
- Make WIP visible. Boards, floor markings and visual management show the queue before it becomes a problem.
To see where WIP builds up, the value stream map shows the inventory triangles between steps.
How to apply the WIP limit on the shop floor
In the previous example, the total WIP limit was 240 parts. Distribute that limit among the steps and make it visible on a board or with floor markings:
| Step | WIP limit (parts) | Rule |
|---|---|---|
| Cutting | 60 | When it reaches 60, cutting stops and helps the next step |
| Machining | 80 | Bottleneck: it must never run out of parts, so it gets the highest limit |
| Assembly | 60 | Only receives what it can assemble at the takt pace |
| Painting | 40 | Lower limit because of space and the cost of each part |
The rule is simple: you only produce when there is free space in the next step. Over time, adjust the limits based on the result: if a step stops for lack of parts, the limit is too low. If WIP keeps building up, it is too high, or there is a flow problem to solve.
The same logic applies outside the factory. In offices, hospitals and development teams, WIP is the tasks, patients or orders in progress. Limiting what is in progress speeds up the completion of what has already started. See the application in Lean Office.
Metrics to track WIP
| Metric | Formula | What it is for |
|---|---|---|
| Total WIP | Sum of the parts in process | Control the level of in-process inventory |
| WIP per step | Parts at each point of the flow | Locate where the queue forms |
| Lead time | WIP ÷ throughput | Predict the production lead time |
| WIP value | Parts × average cost | Measure the tied-up capital |
| WIP coverage | WIP value ÷ daily production cost | Compare WIP with the factory's pace |
Track the series over time. A single measurement says little. WIP that grows without an increase in throughput is a warning of a flow or quality problem.
Common mistakes when handling WIP
- Confusing WIP with safety stock. The first is in process, the second is a planned reserve. See safety stock.
- Reducing only on the count. Without changing the cause (setup, quality, scheduling), the WIP comes back.
- Taking WIP out everywhere at once. Reduce gradually and protect the bottleneck.
- Not counting hidden WIP. Parts on carts, side tables and in rework also count.
- Ignoring scheduling. Releasing orders too early fills the factory. See production planning and control.
Frequently asked questions
What is WIP?
It is work in process (work in progress): material that has entered production and has not yet become a finished product, whether being processed or waiting for the next operation.
How do you calculate WIP?
By directly counting the parts in process at each step, or by Little's Law: WIP = throughput × lead time. In a process with 120 parts per hour and a lead time of 4 hours, WIP is 480 parts.
What does Little's Law say?
In a stable process, the average number of items in the system equals the throughput multiplied by the average time each item takes to go through it. That is why reducing WIP reduces lead time if throughput is maintained.
Is high WIP always bad?
A minimum level is needed to keep the flow going and protect the bottleneck. The problem is the excess, which lengthens lead time, hides defects and ties up capital.
What is the difference between WIP and inventory?
WIP is a type of inventory: the one that is in process. The other types are raw material and finished goods.
How do you reduce WIP?
By limiting WIP per step (kanban), reducing batches with quick setups, balancing the flow to takt time, eliminating stoppages, leveling production and making WIP visible.
Sources
- LITTLE, J. D. C. A Proof for the Queuing Formula: L = λW. Operations Research, v. 9, n. 3, 1961.
- HOPP, W. J.; SPEARMAN, M. L. Factory Physics. McGraw-Hill.
- ROTHER, M.; SHOOK, J. Learning to See. Lean Enterprise Institute.
- IAS 2 Inventories. IFRS Foundation.
This article is a teaching guide. The numerical examples are fictional and only show how the calculation works; use your own company's data and criteria. For questions about standards or manuals, consult the official document. See also the learning paths and the A–Z glossary.
Want to measure your line's performance?
Download the free Metrics That Matter e-book, with OEE, takt time and visual management.
Download the e-book
