A paper value stream map pinned to a visual management board beside an organized assembly line in a factory.

What a future state value stream map is

A future state value stream map shows the value stream the plant wants in 6 to 12 months: production pulled by customer demand, small controlled inventories, continuous flow wherever possible and a single scheduling point. It is drawn from the current state map and answers one question: what must change so the product flows at the customer's pace?

It is not a long-term dream and not a layout redesign. It is a map with numeric targets (lead time, inventory, number of operators) and an implementation plan with dates and owners.

The 8 key questions of the future state

Rother and Shook's method in Learning to See guides the design with 8 questions, always asked in the same order:

  1. What is the takt time? Available time ÷ customer demand. See the takt time calculation.
  2. Build to a finished goods supermarket or directly to shipping? It depends on variety, customer lead time and the cost of holding stock.
  3. Where can you use continuous flow? In processes with cycle time close to or below takt and no long changeovers. See one-piece flow and the U-shaped cell.
  4. Where do you need a supermarket with pull? Where continuous flow is not feasible: long changeovers, large batches, distant suppliers or shared capacity.
  5. What is the single scheduling point (the pacemaker process)? The process that receives the schedule and sets the pace for everything upstream.
  6. How do you level the mix at the pacemaker? See heijunka.
  7. What increment of work do you release to the pacemaker? That is the production pitch: takt × pack-out quantity.
  8. What process improvements are needed? Quick changeover, machine reliability, scrap reduction, line balancing.
Advertisement

Future state map at a glance

The map sums up the 8 questions, the numeric example in this article and the steps of the implementation plan.

FUTURE STATE VSM
Visual map 238: Future State Value Stream Map: How to Design It, Step by Step. Click the map to see it full size.Download the map as PNG

Example: the current state

A fictional line making metal brackets. Demand is 450 pieces per day on one 8-hour shift with 30 minutes of scheduled breaks (two 15-minute breaks). Available time = 28,800 − 1,800 = 27,000 s. Takt = 27,000 ÷ 450 = 60 s.

StepCycle time (s)Inventory after the step (pcs)Inventory (days)
Raw material—1,3503.0
Cutting401,8004.0
Press309002.0
Welding554501.0
Assembly50900 (finished goods)2.0
Total1755,40012.0

Inventory in days = pieces ÷ 450. The stream has a 12-day lead time for only 175 seconds of value-adding work. Value-added ratio = 175 ÷ (12 × 27,000) = 0.05%. Every cycle time is below takt: the capacity exists, the problem is the pushed batch between steps.

Example: the future state

Applying the questions to the case:

InventoryCurrent (days)Future (days)
Raw material3.01.0 (450 pcs)
Cutting → Press4.00.2 (FIFO lane of 90)
Press → Welding2.01.0 (supermarket of 450)
Welding → Assembly1.00 (continuous flow)
Finished goods2.01.0 (450)
Total12.03.2

Lead time drops from 12 to 3.2 days: a cut of 8.8 days, or 73.3%. Inventory falls from 5,400 to 1,440 pieces. Value-added time stays at 175 s and the ratio becomes 175 ÷ (3.2 × 27,000) = 0.20%. The gain comes from the inventory removed, not from working faster. To measure the financial effect, use value stream costing.

Advertisement

Implementation plan: by loops, starting at the pacemaker

Rother and Shook recommend splitting the future state into loops and implementing from the customer backwards, starting with the pacemaker loop. Each loop has an objective, an action, a metric and a deadline. In the example (fictional dates):

LoopWhat to doMetricTiming
1. PacemakerBuild the Welding + Assembly cell, a 30-minute pitch and a finished goods supermarketCycle ≤ 60 s; 15 withdrawals/day metWeeks 1 to 6
2. Press and Cutting450-piece supermarket, production kanban, FIFO lane, quick changeover on the pressStock ≤ 1 day; changeover within targetWeeks 7 to 12
3. Raw materialFrequent supplier deliveries and a replenishment routeRaw material ≤ 1 dayWeeks 13 to 18

The press is where quick changeover matters most: see SMED. For supermarket replenishment, see the internal milk run. Labor for each loop comes from takt-based staffing.

Review the plan every 4 weeks at the gemba, comparing target and reality. When the future state is reached, it becomes the new current state and the cycle restarts.

Common mistakes

Frequently asked questions

What is a future state VSM?

It is the map of the desired value stream, with continuous flow, supermarkets, pull and one scheduling point, together with a plan to get there.

How many questions guide the future state?

Eight, in order: takt, shipping, continuous flow, supermarkets, scheduling point, mix leveling, work increment (pitch) and required improvements.

How do you decide where to use continuous flow?

In sequential processes with a cycle time equal to or below takt, no long changeover and good reliability. In the example, Welding and Assembly.

What time horizon does the future state have?

Usually 6 to 12 months, split into loops implemented in sequence, starting with the pacemaker.

How much can lead time fall?

It depends on the current state. In this article's example, from 12 to 3.2 days (73.3%), because inventory between steps was cut. The numbers are illustrative.

Who builds the future state map?

A team that includes production, quality, maintenance and logistics, led by the person who owns the value stream end to end.

Advertisement

Sources

  1. ROTHER, M.; SHOOK, J. Learning to See: Value Stream Mapping to Add Value and Eliminate Muda. Cambridge: Lean Enterprise Institute.
  2. ROTHER, M.; HARRIS, R. Creating Continuous Flow. Cambridge: Lean Enterprise Institute, 2001.
  3. WOMACK, J. P.; JONES, D. T. Lean Thinking. New York: Free Press.

Keep studying: trusted sources and links

Save this address: Manufatura Enxuta is your school for lean manufacturing. Come back whenever you need to study, with a complete article, a visual map and trusted sources. Follow one of the learning paths or check the A–Z glossary.

Want to lead change with a method?

Download the free e-book Lean for Leaders and see how to sustain lean culture day to day.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.