Quick answer: the quality metrics most used in production are first pass yield (FPY), the scrap and rework rates, PPM (defective parts per million), DPMO, Cpk and the cost of poor quality. Choose a few, define each formula clearly and break results down by cause so you can act.
- What are quality metrics
- The main metrics and their formulas
- Worked example: a lot of 10,000 parts
- Outcome metrics and process metrics
- How to set realistic targets
- How to collect data reliably
- How to build a simple quality dashboard
- From number to action
- Common mistakes with quality metrics
- Frequently asked questions
What are quality metrics
Quality metrics turn quality into numbers. They answer simple questions: how many parts come out good the first time? How many become scrap? How many reach the customer with a defect? How much does that cost?
They serve three purposes: to see performance, to compare shifts, lines and periods and to decide where to act. A metric with no action attached becomes board decoration. So next to each number, you need to know who looks at it, how often and what they do when it misses the target.
The main metrics and their formulas
| Metric | Formula | What it shows |
|---|---|---|
| FPY (first pass yield) | Parts good the first time ÷ parts started × 100 | Process effectiveness without rework. See FPY and RTY |
| Scrap rate | Parts scrapped ÷ parts produced × 100 | Permanent loss of material and labor |
| Rework rate | Parts reworked ÷ parts produced × 100 | The hidden cost of doing it again |
| PPM (parts per million) | Defective parts ÷ parts delivered × 1,000,000 | Quality as the customer perceives it. See PPM |
| DPMO | Defects ÷ (units × defect opportunities) × 1,000,000 | Basis of the sigma level, comparable across products |
| Cp and Cpk | Capability of the characteristic relative to the tolerance | Ability to produce within specification. See Cp and Cpk |
| Cost of poor quality | Scrap cost + rework + warranty + complaints | Financial impact. See cost of quality |
| Corrective action closure time | Days between opening and closing an action | Speed of response to problems |
Point of attention: always define the denominator. "Scrap rate" over parts started, produced or approved gives different numbers. Choose one and standardize it.
Worked example: a lot of 10,000 parts
A teaching example. A line started 10,000 parts in the month. From the data collected: 250 were scrapped, 600 were reworked and recovered, and the customer returned 3 of the shipped parts. The 850 defective parts from the line had 1,250 defects in total, and each part has 5 defect opportunities. Costs: scrap of $40 per part and rework of $6 per part.
| Metric | Calculation | Result |
|---|---|---|
| Good the first time | 10,000 − 250 − 600 | 9,150 parts |
| FPY | 9,150 ÷ 10,000 × 100 | 91.5% |
| Scrap rate | 250 ÷ 10,000 × 100 | 2.5% |
| Rework rate | 600 ÷ 10,000 × 100 | 6.0% |
| Total approved parts | 9,150 + 600 | 9,750 parts |
| Final yield | 9,750 ÷ 10,000 × 100 | 97.5% |
| Internal PPM | 850 ÷ 10,000 × 1,000,000 | 85,000 ppm |
| External PPM | 3 ÷ 9,750 × 1,000,000 | about 308 ppm |
| DPMO | 1,250 ÷ (10,000 × 5) × 1,000,000 | 25,000 |
| Cost of poor quality | 250 × $40 + 600 × $6 | $10,000 + $3,600 = $13,600 |
Reading. A final yield of 97.5% looks good, but the FPY of 91.5% shows that 8.5% of the parts go through scrap or rework. The $13,600 cost sits inside that hidden "good". The external PPM is much lower than the internal one, which indicates that final inspection catches most of the defects, but that is expensive and does not solve the cause.
For reference, a DPMO of 25,000 corresponds to about 3.5 sigma, using the usual 1.5 sigma shift convention. Conversion tables vary; use the same one to compare periods.
Note: fictional values to illustrate the calculations. Real costs include material, labor, energy and, for rework, machine time.
Outcome metrics and process metrics
Not every metric arrives at the same time. Combine the two types:
| Type | Examples | Characteristic |
|---|---|---|
| Outcome (lagging) | External PPM, customer complaints, cost of poor quality | Show what has already happened and the effect on the customer and the results |
| Process (leading) | FPY, scrap and rework per shift, Cpk, process audits | Show what is happening and let you act before the customer is affected |
If you only measure external PPM, you find problems late, and after costly inspection. Process metrics flag deviations while there is still time to correct them. Audits, such as the VDA 6.3 process audit and layered process audits, complete the picture.
How to set realistic targets
A well-formed target has a number, a deadline and a plan. Continuing the example of 10,000 parts per month, with an FPY of 91.5%:
- Target: reduce scrap from 250 to 150 parts and rework from 600 to 400 parts in six months.
- Effect on FPY: good the first time = 10,000 − 150 − 400 = 9,450, or 94.5%.
- Monthly gain: 100 fewer scrapped parts × $40 = $4,000, plus 200 fewer reworked parts × $6 = $1,200, a total of $5,200 per month.
- Plan: Pareto of the defects, actions on the two biggest causes and a monthly check of the effect.
Notice that the FPY target comes from adding up the scrap and rework targets, tied to actions. Without a plan, a target is a wish. The money gain also helps prioritize: actions that solve scrap are worth more per part than those for rework.
How to collect data reliably
- Record at the point of generation. The operator notes scrap and rework at the station, with the reason, on a simple form or a data collector.
- Standardize defect codes. A short, clear list, so everyone classifies in the same way.
- Separate counting from judgment. The person who inspects should not be measured by the index they record.
- Audit the data. Compare the record with the physical scrap count and with material consumption.
- Give quick feedback. The people who record need to see the result on the board, or they stop noting it down.
How to build a simple quality dashboard
Less is more. Five to seven well-defined metrics are worth more than twenty numbers with no owner.
| Metric | Frequency | Who looks | Action when off target |
|---|---|---|---|
| FPY per line | Daily | Line leader | 10-minute meeting at the board |
| Scrap and rework (% and $) | Daily and weekly | Supervisor and quality | Pareto of causes and corrective action |
| External PPM | Monthly | Quality and management | Cause analysis and response to the customer |
| Cpk of critical characteristics | Per lot or weekly | Quality and process | Stronger control and process adjustment |
| Cost of poor quality | Monthly | Management | Prioritizing improvement projects |
Show the dashboard at the workplace, with simple charts, a visible target and owners. See best practices in the production dashboard article and in visual management.
From number to action
A metric only has value when it leads to a decision. A practical path:
- Break down the result by product, machine, shift and defect type.
- Prioritize with the Pareto chart: a few defects account for most of the problem.
- Look for the cause with the Ishikawa diagram and the 5 Whys.
- Prevent recurrence with poka-yoke, standard work and a control plan.
- Verify the effect on the same metric, over the same comparison period.
To track process stability over time, use statistical process control. To decide between recovering and discarding, see rework vs scrap. The 7 basic quality tools bring the whole set together.
Common mistakes with quality metrics
- Measuring only what reaches the customer. External PPM is a lagging metric. FPY and scrap warn you earlier.
- A different denominator every month. Standardize the definition.
- A target without a method. A zero-defect target with no plan turns into frustration. Combine the target with action.
- Hiding rework. If nobody records it, the cost does not show up and the cause is not addressed.
- Chasing the number, not the cause. Pressure for results without analysis encourages recording errors.
- Too many metrics. When everything is a priority, nothing is.
- Unreliable data. Confirm the measurement system with MSA.
Frequently asked questions
What are the main quality metrics in production?
FPY (first pass yield), scrap rate, rework rate, PPM, DPMO, Cp and Cpk, cost of poor quality and corrective action closure time.
How do you calculate PPM?
Divide the number of defective parts by the number of parts delivered and multiply by 1,000,000. Example: 3 returned out of 9,750 shipped gives about 308 ppm.
What is FPY?
It is first pass yield: the proportion of parts that are good the first time, with no rework or scrap. In the example, 9,150 out of 10,000, or 91.5%.
What is the difference between scrap and rework?
Scrap is the part that is discarded, with a loss of material and labor. Rework is the part recovered with additional work, which still costs money and time.
How many quality metrics should I track?
Five to seven, well defined, with an owner, a frequency and a reaction plan. Too many metrics dilute the focus.
What is DPMO?
Defects per million opportunities: defects ÷ (units × defect opportunities per unit) × 1,000,000. It is the basis for the sigma level.
Sources
- ASQ. The Quality Toolbox. Milwaukee: ASQ Quality Press.
- MONTGOMERY, D. C. Introduction to Statistical Quality Control. Hoboken: Wiley.
- ISO 9001: Quality management systems. Requirements.
- Lean Enterprise Institute, general reference on lean: https://www.lean.org/
This article is a teaching guide. The numerical examples are fictional and only show how the calculation works; use your own company's data and criteria. For questions about standards or manuals, consult the official document. See also the learning paths and the A–Z glossary.