What is the master production schedule (MPS)

The master production schedule (MPS) states how much of each finished product will be built in each period of the planning horizon, usually weeks. It turns the aggregate sales and operations plan into quantities and dates, and feeds MRP, which calculates components and materials.

In practice the MPS answers one question: given my forecast, booked orders, inventory and capacity, what will I build and when? It is the central link of production planning and control.

Visual map of the master production schedule

The map shows where the MPS sits between S&OP and MRP and the period table of the worked example below.

MASTER PRODUCTION SCHEDULE (MPS)
Visual map 113: Master Production Schedule (MPS): How to Build One. Click the map to see it full size.Download the map as PNG

Where the MPS fits

Inputs are the demand forecast, firm orders, beginning inventory, lot size and safety stock.

Advertisement

Worked example: 8 weeks

Data: beginning inventory of 50 units, fixed lot of 100, zero safety stock. In each week, demand is the larger of forecast and firm orders. Projected on-hand (POH) is:

POH(t) = POH(tβˆ’1) + MPS(t) βˆ’ demand(t); schedule a lot when POH(tβˆ’1) βˆ’ demand(t) < 0

Week 1: 50 βˆ’ 70 = βˆ’20, negative, so a lot of 100 is scheduled and POH becomes 50 + 100 βˆ’ 70 = 80. Week 2: 80 βˆ’ 60 = 20, no lot. Week 3: 20 βˆ’ 70 = βˆ’50, a lot of 100 is scheduled and POH is 50. The full result:

ItemWk 1Wk 2Wk 3Wk 4Wk 5Wk 6Wk 7Wk 8
Forecast6060707080809090
Firm orders7055402510000
Demand used7060707080809090
MPS (lot 100)100–100100–100100100
Projected on-hand802050800203040
ATP25–6065–100100100

Check: 50 beginning + 600 produced βˆ’ 610 demand = 40, equal to week 8 inventory. Six lots of 100 cover the eight weeks, averaging 75 per week against an average demand of 76.25.

ATP: how much can I promise a customer

ATP (Available to Promise) is the part of the MPS not yet committed to orders, up to the next lot. In the first week it includes beginning inventory.

ATP(week 1) = beginning inventory + MPS βˆ’ orders until next MPS; other weeks: MPS βˆ’ orders until next MPS

Week 1: 50 + 100 βˆ’ (70 + 55) = 25. Week 3: 100 βˆ’ 40 = 60. Week 4: 100 βˆ’ (25 + 10) = 65. Weeks 6, 7 and 8 have no orders and keep 100 each. If sales wants to promise 80 units for week 3, the ATP of 60 shows the lot must be moved earlier or another one created.

Advertisement

Capacity check (RCCP)

The MPS is only valid if it fits capacity. The rough-cut check uses the bottleneck resource. Assume 0.2 h per unit at the bottleneck and 25 h available per week:

ItemWk 1Wk 2Wk 3Wk 4Wk 5Wk 6Wk 7Wk 8
MPS100–100100–100100100
Bottleneck hours20020200202020
Load80%0%80%80%0%80%80%80%

Each lot of 100 takes 100 Γ— 0.2 = 20 h, or 20 Γ· 25 = 80% of capacity. Average load is (600 Γ— 0.2) Γ· (8 Γ— 25) = 120 Γ· 200 = 60%. If a lot exceeded 25 h, you would need to split it, build part earlier or adjust capacity. See how to calculate production capacity and constraints in the theory of constraints.

Horizon, time fences and leveling

For inventory sizing, see inventory management.

Common mistakes

Frequently asked questions

What is the MPS in manufacturing?

The master production schedule: quantities of finished products to build in each period of the horizon.

What is the difference between MPS and MRP?

The MPS sets what and how much finished product to build; MRP calculates the components and materials needed to meet it.

How do I calculate projected on-hand in the MPS?

POH(t) = POH(tβˆ’1) + MPS(t) βˆ’ demand(t). When the result would be negative, schedule a lot.

What is ATP?

Available to Promise: the MPS minus the orders already committed until the next lot.

What are time fences?

Time windows in which the MPS does not change, or changes only with approval, to keep production and purchasing stable.

How long should the MPS horizon be?

At least the product's cumulative lead time. In many plants, 8 to 12 weeks.

Advertisement

Sources

  1. VOLLMANN, T. E. et al. Manufacturing Planning and Control for Supply Chain Management. McGraw-Hill.
  2. ASCM (APICS). Dictionary.
  3. ORLICKY, J. Material Requirements Planning. McGraw-Hill, 1975.
  4. STEVENSON, W. J. Operations Management. McGraw-Hill.

Want a quick reference guide for the factory floor?

Download the free Pocket Guide e-book with the Lean tools summarized on one page each.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.