Quick answer: Kanban manages the continuous flow of work: it visualizes the stages, limits work in progress and pulls new tasks as capacity allows. Scrum organizes work in fixed cycles (sprints), with defined roles and meetings. Kanban adapts to variable demand. Scrum works well when there is a short goal and deadline.

Advertisement

Where the two come from

Kanban was born in the Toyota Production System as a card that signals the need to replenish or produce, pulling production from consumption. See the kanban guide and the calculation of the number of cards.

The Kanban Method applied to knowledge work (software, services, projects) was systematized by David J. Anderson, from manufacturing kanban, in the 2000s. Scrum was created by Ken Schwaber and Jeff Sutherland, in software development, and is described in the Scrum Guide. You should verify dates and versions in the official guides.

In this article, "kanban" means the visual flow management method, which applies to the factory as well as to project teams.

How each one works

Kanban in a few words:

Scrum in a few words:

Side-by-side comparison

AspectKanbanScrum
CadenceContinuous flowFixed-length sprints
RolesDoes not require new rolesProduct Owner, Scrum Master and Developers
Changes along the wayAccepted at any timePreferably between sprints
WIP limitCentral, per stageIndirect, through sprint capacity
MeetingsOptional, defined by the teamEvents defined by the method
Typical metricCycle time and throughputVelocity and delivery of the sprint goal
CommitmentTo the flowTo the sprint goal
Best forVariable, continuous demandProjects with a short goal and deadline

In industry: where each one fits

SituationTends to work betterWhy
Replenishing parts between stations (pull production)KanbanConsumption signal and continuous flow
Maintenance requests and small improvements that arrive all the timeKanbanVariable demand, priority changes
Improvement project with a clear goal, such as reducing setup in 30 daysScrumGoal, deadline and frequent review
New product development, with several partial deliveriesScrumIncrements and customer feedback
Engineering team with mixed projects and requestsScrumbanA mix of rhythm and flow

For applying Scrum to improvement projects, see Scrum in industry.

What about Scrumban?

Scrumban is a combination: the team uses Scrum's sprints and roles, but manages the work inside the sprint with a kanban board and WIP limits. It is usually useful when the team has a project agenda but receives urgent demands along the way. It is not an official method. Define clear rules for what goes into the sprint and what goes straight into the flow.

How to choose for your team

  1. Observe the nature of the demand. Does it arrive little by little and without warning (kanban) or can it be planned in blocks (scrum)?
  2. Look at the stability of priorities. If they change every day, fixed cycles create friction.
  3. Check whether there is a clear goal. If there is a short goal and deadline, the sprint helps.
  4. Consider team size and experience. Scrum asks for more discipline in roles and events. Kanban is easier to start.
  5. Start simple. Many teams start with kanban and then add elements of Scrum when they need them.
  6. Reassess. After two or three cycles, adjust what did not work.
Advertisement

Metrics: how each one tracks the work

In kanban, the most used measures are cycle time (how long a task takes from start to finish), throughput (tasks completed per period) and WIP. The three are related by Little's Law.

Average cycle time = average WIP ÷ throughput

Fictional example: an improvement team has on average 12 tasks in progress and completes 3 per week. The average cycle time is 12 ÷ 3 = 4 weeks. If the WIP limit falls to 6 and throughput holds, the cycle time falls to 2 weeks.

In Scrum, velocity (amount of work completed per sprint) and the fulfillment of the sprint goal are used. Velocity serves to plan the team and should not be used to compare different teams.

Practical example: a maintenance and improvement team

Fictional example. A team of six people handles maintenance calls (urgent and variable) and also has a quarterly project to reduce stoppages. A simple split:

Type of workMethodHow it looks
Maintenance callsKanbanBoard with the columns New, In progress, Waiting for part and Done, with a WIP limit on In progress
Stoppage reduction projectScrum, two-week sprintsA goal for each sprint, planning meeting, review with production and retrospective
CapacityCombinedPart of the capacity reserved for calls; the rest for the project

The point is to choose the method by the nature of the work, not by fashion.

How to start with kanban in one week

  1. List the current work and draw the real flow, from request to delivery.
  2. Build a board with the columns of the flow, on a wall or digital.
  3. Put each task on a card and place it in the right column.
  4. Set a WIP limit per column, starting with a value that is uncomfortable but feasible.
  5. Hold a short daily meeting in front of the board.
  6. Review the board weekly and adjust the limits.

Common mistakes

Frequently asked questions

What is the main difference between Kanban and Scrum?

Kanban manages continuous flow, with a limit on work in progress. Scrum organizes work in fixed-length cycles (sprints), with defined roles and meetings.

Can Kanban and Scrum be used together?

Yes. That is the case with Scrumban: the team uses Scrum's sprints and roles, but manages the work inside the sprint with a kanban board and WIP limits.

Which is better for industry?

It depends on the work. For replenishment and continuous flow, kanban. For improvement projects with a short goal and deadline, Scrum can help. Many areas use both in different contexts.

Is factory kanban the same as software kanban?

They share the same origin and the same logic of pulling work as capacity allows. Factory kanban uses cards to replenish materials. The Kanban Method applies the idea to knowledge work, with WIP limits and flow metrics.

How long does Scrum require sprints to be?

According to the Scrum Guide, one month at most. Many teams use between one and four weeks. Check the current version of the official guide.

Where to start: kanban or scrum?

For most teams, kanban is simpler to start: visualize the work, limit WIP and improve little by little. Adopt elements of Scrum if you need cycles and goals.

Sources

  1. SCHWABER, K.; SUTHERLAND, J. The Scrum Guide. 2020. Available at scrumguides.org (confirm the current version). https://scrumguides.org/
  2. ANDERSON, D. J. Kanban: Successful Evolutionary Change for Your Technology Business. Sequim: Blue Hole Press, 2010.
  3. OHNO, T. Toyota Production System: Beyond Large-Scale Production. Portland: Productivity Press, 1988.

This article is a teaching guide. The numerical examples are fictional and only show how the calculation works; use your own company's data and criteria. For questions about standards or manuals, consult the official document. See also the learning paths and the A–Z glossary.

Want to implement pull production?

Download the free e-book Pull Production and see how to size kanban and the supermarket.

Download the e-book
Advertisement
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.