Quick answer: Kanban manages the continuous flow of work: it visualizes the stages, limits work in progress and pulls new tasks as capacity allows. Scrum organizes work in fixed cycles (sprints), with defined roles and meetings. Kanban adapts to variable demand. Scrum works well when there is a short goal and deadline.
- Where the two come from
- How each one works
- Side-by-side comparison
- In industry: where each one fits
- What about Scrumban?
- How to choose for your team
- Metrics: how each one tracks the work
- Practical example: a maintenance and improvement team
- How to start with kanban in one week
- Common mistakes
- Frequently asked questions
Where the two come from
Kanban was born in the Toyota Production System as a card that signals the need to replenish or produce, pulling production from consumption. See the kanban guide and the calculation of the number of cards.
The Kanban Method applied to knowledge work (software, services, projects) was systematized by David J. Anderson, from manufacturing kanban, in the 2000s. Scrum was created by Ken Schwaber and Jeff Sutherland, in software development, and is described in the Scrum Guide. You should verify dates and versions in the official guides.
In this article, "kanban" means the visual flow management method, which applies to the factory as well as to project teams.
How each one works
Kanban in a few words:
- A board with columns that represent the stages of the work (to do, in progress, done).
- Work-in-progress (WIP) limit per column: something new only enters when something leaves. See WIP.
- Continuous flow: tasks enter at any time, with no fixed cycle.
- Flow metrics: cycle time, throughput and work item age.
Scrum in a few words:
- Work in fixed-length cycles called sprints (according to the Scrum Guide, of one month at most).
- Three accountabilities: Product Owner (value and priority), Scrum Master (support for the method) and Developers (those who do the work).
- Events: sprint planning, daily meeting, review and retrospective.
- Artifacts: product backlog, sprint backlog and the delivered increment.
Side-by-side comparison
| Aspect | Kanban | Scrum |
|---|---|---|
| Cadence | Continuous flow | Fixed-length sprints |
| Roles | Does not require new roles | Product Owner, Scrum Master and Developers |
| Changes along the way | Accepted at any time | Preferably between sprints |
| WIP limit | Central, per stage | Indirect, through sprint capacity |
| Meetings | Optional, defined by the team | Events defined by the method |
| Typical metric | Cycle time and throughput | Velocity and delivery of the sprint goal |
| Commitment | To the flow | To the sprint goal |
| Best for | Variable, continuous demand | Projects with a short goal and deadline |
In industry: where each one fits
| Situation | Tends to work better | Why |
|---|---|---|
| Replenishing parts between stations (pull production) | Kanban | Consumption signal and continuous flow |
| Maintenance requests and small improvements that arrive all the time | Kanban | Variable demand, priority changes |
| Improvement project with a clear goal, such as reducing setup in 30 days | Scrum | Goal, deadline and frequent review |
| New product development, with several partial deliveries | Scrum | Increments and customer feedback |
| Engineering team with mixed projects and requests | Scrumban | A mix of rhythm and flow |
For applying Scrum to improvement projects, see Scrum in industry.
What about Scrumban?
Scrumban is a combination: the team uses Scrum's sprints and roles, but manages the work inside the sprint with a kanban board and WIP limits. It is usually useful when the team has a project agenda but receives urgent demands along the way. It is not an official method. Define clear rules for what goes into the sprint and what goes straight into the flow.
How to choose for your team
- Observe the nature of the demand. Does it arrive little by little and without warning (kanban) or can it be planned in blocks (scrum)?
- Look at the stability of priorities. If they change every day, fixed cycles create friction.
- Check whether there is a clear goal. If there is a short goal and deadline, the sprint helps.
- Consider team size and experience. Scrum asks for more discipline in roles and events. Kanban is easier to start.
- Start simple. Many teams start with kanban and then add elements of Scrum when they need them.
- Reassess. After two or three cycles, adjust what did not work.
Metrics: how each one tracks the work
In kanban, the most used measures are cycle time (how long a task takes from start to finish), throughput (tasks completed per period) and WIP. The three are related by Little's Law.
Average cycle time = average WIP ÷ throughput
Fictional example: an improvement team has on average 12 tasks in progress and completes 3 per week. The average cycle time is 12 ÷ 3 = 4 weeks. If the WIP limit falls to 6 and throughput holds, the cycle time falls to 2 weeks.
In Scrum, velocity (amount of work completed per sprint) and the fulfillment of the sprint goal are used. Velocity serves to plan the team and should not be used to compare different teams.
Practical example: a maintenance and improvement team
Fictional example. A team of six people handles maintenance calls (urgent and variable) and also has a quarterly project to reduce stoppages. A simple split:
| Type of work | Method | How it looks |
|---|---|---|
| Maintenance calls | Kanban | Board with the columns New, In progress, Waiting for part and Done, with a WIP limit on In progress |
| Stoppage reduction project | Scrum, two-week sprints | A goal for each sprint, planning meeting, review with production and retrospective |
| Capacity | Combined | Part of the capacity reserved for calls; the rest for the project |
The point is to choose the method by the nature of the work, not by fashion.
How to start with kanban in one week
- List the current work and draw the real flow, from request to delivery.
- Build a board with the columns of the flow, on a wall or digital.
- Put each task on a card and place it in the right column.
- Set a WIP limit per column, starting with a value that is uncomfortable but feasible.
- Hold a short daily meeting in front of the board.
- Review the board weekly and adjust the limits.
Common mistakes
- Using a kanban board without a WIP limit: it becomes just a task list.
- Applying Scrum without a clear Product Owner: nobody decides the priority.
- Forcing sprints on continuous-flow work, such as handling maintenance calls.
- Ignoring the retrospective and the improvement of the method itself.
- Copying the vocabulary without the principle: saying "sprint" for a one-week deadline, with no goal or review.
Frequently asked questions
What is the main difference between Kanban and Scrum?
Kanban manages continuous flow, with a limit on work in progress. Scrum organizes work in fixed-length cycles (sprints), with defined roles and meetings.
Can Kanban and Scrum be used together?
Yes. That is the case with Scrumban: the team uses Scrum's sprints and roles, but manages the work inside the sprint with a kanban board and WIP limits.
Which is better for industry?
It depends on the work. For replenishment and continuous flow, kanban. For improvement projects with a short goal and deadline, Scrum can help. Many areas use both in different contexts.
Is factory kanban the same as software kanban?
They share the same origin and the same logic of pulling work as capacity allows. Factory kanban uses cards to replenish materials. The Kanban Method applies the idea to knowledge work, with WIP limits and flow metrics.
How long does Scrum require sprints to be?
According to the Scrum Guide, one month at most. Many teams use between one and four weeks. Check the current version of the official guide.
Where to start: kanban or scrum?
For most teams, kanban is simpler to start: visualize the work, limit WIP and improve little by little. Adopt elements of Scrum if you need cycles and goals.
Sources
- SCHWABER, K.; SUTHERLAND, J. The Scrum Guide. 2020. Available at scrumguides.org (confirm the current version). https://scrumguides.org/
- ANDERSON, D. J. Kanban: Successful Evolutionary Change for Your Technology Business. Sequim: Blue Hole Press, 2010.
- OHNO, T. Toyota Production System: Beyond Large-Scale Production. Portland: Productivity Press, 1988.
This article is a teaching guide. The numerical examples are fictional and only show how the calculation works; use your own company's data and criteria. For questions about standards or manuals, consult the official document. See also the learning paths and the A–Z glossary.