What supplier kanban is

Supplier kanban extends the pull signal beyond your plant: when the customer consumes a container, a card (or electronic signal) goes back to the supplier, who replenishes only what was used. Instead of weekly orders driven by a forecast, deliveries follow real consumption.

The math is the same as for internal kanban, but the replenishment time now includes card return, picking or production at the supplier, transport and receiving. If the base calculation is new to you, start with how to size a kanban loop.

Advertisement

Visual map of supplier kanban

The map shows the replenishment loop, the card formula and the effect of container size in the 400-pieces-per-day example.

SUPPLIER KANBAN
Visual map 294: Supplier Kanban: Signal, Card Formula and Worked Example. Click the map to see it full size.Download the map as PNG

Signal types between customer and supplier

The signal must be simple, visible and unique per container. Four formats are common:

SignalHow it worksWhen to use
Physical cardThe card travels with the container and goes back to the supplier on the delivery route when it is emptiedFew items, nearby supplier, daily deliveries
Electronic card (e-kanban)Scanning the card barcode alerts the supplier through a system or portalDistant supplier, many items, need for traceability
Two-binWhen the first bin empties, the second becomes the working stock and the empty bin is the replenishment signalCheap, small items such as fasteners
Colored-zone boardGreen, yellow and red zones show the item level at the customerIrregular consumption with fixed delivery routes

Stable, low-variety items are the best candidates. For the pickup route and frequent small deliveries, a milk run usually carries both signal and material.

Card quantity formula

N = D × T × (1 + S) ÷ C

D is daily demand, T is the total replenishment loop time in days (from the container being emptied to its return full), S is the safety allowance (%) and C is the container quantity. Always round up. Maximum stock of the part is N × C.

Worked example: a fastener at 400 pieces per day

Fictional example: a line uses 400 pieces per day of a purchased item, packed in containers of 50. The supplier is 120 km away and delivers twice a day. The loop time was measured on the floor:

Loop stepTime (days)
Empty container becomes a signal and the card reaches the supplier0.25
Picking or production at the supplier0.75
Transport to the plant0.50
Receiving and delivery to the point of use0.50
Total (T)2.00

With a 10% allowance (S = 0.10):

N = 400 × 2.0 × 1.10 ÷ 50 = 880 ÷ 50 = 17.6 → 18 cards

Maximum stock is 18 × 50 = 900 pieces. Consumption is 8 containers per day (400 ÷ 50), so with two deliveries each trip brings 4 containers. With traditional weekly buying, the same item would arrive in lots of 2,000 pieces (5 days × 400), and maximum stock would be at least 2,000, more than twice the kanban level.

Advertisement

Effect of container size

The same demand and the same T give different results by container size. Rounding up can inflate stock when containers are large:

Container (pcs)Calculated NCardsMaximum stock (pcs)
25880 ÷ 25 = 35.236900
50880 ÷ 50 = 17.618900
100880 ÷ 100 = 8.89900
200880 ÷ 200 = 4.451,000

Small containers give finer response but need more trips and handling. Pick the smallest container the supplier can pack and the carrier can move without raising freight cost per piece.

How to roll out with one supplier, step by step

  1. Select items: A or B class from the ABC analysis, with stable consumption and a dependable supplier.
  2. Measure the real loop step by step and use the recurring worst case, not the ideal average.
  3. Set the standard container: fixed quantity, packaging, labeling and a weight the operator can handle.
  4. Calculate N and print it on the card with part number, description, quantity, delivery point and supplier.
  5. Agree on written rules: deliver only against a card, never more than the card authorizes, quality checked at source.
  6. Run a pilot of 4 to 8 weeks with one or two items and track card return and shortages.
  7. Review N whenever demand or loop time changes, and remove cards gradually to expose problems.

The discipline follows the general rules of kanban: see the golden rules of kanban. If the supplier manages stock inside your plant, compare with VMI and consignment stock.

When it works and when it does not

For those items, MRP remains the better method. Before scaling up, rate the supplier with objective criteria such as a supplier quality index.

Common mistakes

Frequently asked questions

What is supplier kanban?

It is pull replenishment applied to purchased materials: the supplier receives a signal when a container is consumed and delivers only the matching quantity.

How do you calculate the number of cards?

N = D × T × (1 + S) ÷ C, rounded up. In the example, 400 × 2.0 × 1.10 ÷ 50 = 17.6, so 18 cards and at most 900 pieces.

Which is better, physical cards or e-kanban?

Physical cards suit a nearby supplier and few items. E-kanban pays off with distance, many items or a need to trace every signal.

Must the supplier be close to the plant?

No, but the loop time grows with distance and stock grows with it. Distant suppliers call for consolidated deliveries or a small buffer stock.

How is it different from VMI?

In kanban the customer controls the signal and stock sits in the plant. In VMI the supplier monitors and decides replenishment of the customer stock.

Can I use kanban for every purchased item?

No. It fits repetitive items with stable consumption. Make-to-order or highly irregular items are better planned with MRP.

Advertisement

Sources

  1. Taiichi Ohno. Toyota Production System: Beyond Large-Scale Production. Productivity Press.
  2. Yasuhiro Monden. Toyota Production System: An Integrated Approach to Just-In-Time. CRC Press.
  3. James Womack and Daniel Jones. Lean Thinking. Free Press.
  4. Mike Rother and John Shook. Learning to See. Lean Enterprise Institute.
  5. Jeffrey Liker. The Toyota Way. McGraw-Hill.

Keep studying: trusted sources and links

Save this address: Manufatura Enxuta is your school for lean manufacturing. Come back whenever you need to study, with a complete article, a visual map and trusted sources. Follow one of the learning paths or check the A–Z glossary.

Want real pull production?

Download the free pull production e-book, with kanban, supermarkets and leveling.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.