A plant improvement team gathered at a sprint board on the shop floor, with task cards in columns.

What Scrum means for manufacturing improvement

Scrum is an agile framework that organizes work into short cycles of 1 to 4 weeks called sprints, with a prioritized backlog, a small team and a review at the end of each cycle. In a plant it suits improvement projects with many ideas and little available time: the team delivers one concrete improvement per sprint instead of waiting for a long project to close.

Scrum does not replace the shop floor or Lean. It organizes the management of the improvement work, while daily production keeps following the plan and Lean daily management.

Visual map of Scrum applied to improvements

The map shows the roles, the sprint cycle and the 48-point backlog example.

SCRUM FOR PLANT IMPROVEMENT
Visual map 260: Agile Scrum in Manufacturing Improvement Projects. Click the map to see it full size.Download the map as PNG

Roles, events and artifacts

The Scrum Guide (Schwaber and Sutherland) defines three accountabilities, five events and three artifacts. Translated to a plant improvement effort:

ElementIn ScrumIn manufacturing improvement
Product OwnerOwns the backlogManager or engineer who prioritizes by impact on cost, quality or safety
Scrum MasterFacilitates the methodLean coach or improvement lead who removes blockers
TeamDelivers the increment3 to 7 people: operator, maintenance, quality, engineering
BacklogPrioritized listImprovement ideas estimated in points
Sprint1 to 4 week cycleImprovement cycle with a clear goal
Daily15-minute syncStand-up at the station or the board
Review and retrospectiveInspect and adaptShow the result at the gemba and adjust the method

The logic is PDCA at a fixed rhythm: plan at sprint planning, do during the sprint, check at the review and act at the retrospective.

Advertisement

How to build the improvement backlog

The backlog holds everything you want to improve, in priority order. Good sources are operator ideas, audit findings, the value stream map and the 7 wastes. Each item needs three things: a clear description, a definition of done and an estimate.

Estimating in points is relative: it measures effort and uncertainty, not hours. Relabeling tools is a 3, an error-proofing fixture is an 8. The team compares items with each other, often using 1, 2, 3, 5, 8, 13. Anything above 8 should be split.

Example: a 48-point backlog and team velocity

Fictional example: a team of 5 people, 2-week sprints (10 working days) and the backlog below, already in priority order.

RankItemPoints
1Poka-yoke on the torque sensor8
2Start-of-shift checklist4
3Visual management in the cell3
4Tool labeling3
55S kit for the assembly station5
6Work instruction for station 45
7Quick changeover (SMED) on press P28
8Supermarket replenishment8
9Rework in the paint area4
Total48

Velocity is the average of points completed in earlier sprints. In the last three the team closed 11, 14 and 12: (11 + 14 + 12) ÷ 3 = 12.3, rounded to 12 points per sprint.

Sprints needed = backlog points ÷ velocity = 48 ÷ 12 = 4 sprints (8 weeks)

In sprint 1 the team commits to items 1 and 2: 8 + 4 = 12 points, with the goal "stop out-of-spec torque and standardize the start of shift". The ideal burndown falls 1.2 points per working day: 12 left on day 0, 6 on day 5 and 0 on day 10. If the real line sits above the ideal one mid-sprint, the team cuts scope, never quality.

End of sprint1234
Points left in backlog3624120
Advertisement

One sprint cycle in practice

  1. Planning (2 h): the team pulls items up to its velocity and sets the sprint goal.
  2. Daily (15 min): standing at the board: what I finished, what I will do, what blocks me.
  3. Execution: improvements happen at the station with quick trials; the board follows the kanban board logic (to do, doing, done).
  4. Review (1 h): the team shows what changed on site, with before and after data.
  5. Retrospective (1 h): the team decides what to keep and what to change in its own method.

When to use Scrum and when to pick something else

Common mistakes

Frequently asked questions

Does Scrum work in manufacturing?

It works for improvement work, product development and planned maintenance. It is not meant to control production flow itself; kanban and production scheduling do that.

What is the ideal sprint length?

For plant improvements, 2 weeks is usually the balance: short enough to correct course, long enough to test at the station.

What are story points?

A relative measure of effort and uncertainty. They compare items with each other and do not measure hours.

How do I calculate how many sprints a project needs?

Divide the backlog points by the average velocity. In the example, 48 ÷ 12 = 4 sprints.

What is the difference between Scrum and kanban?

Scrum works in fixed cycles with a goal commitment; kanban works as continuous flow with a limit on work in progress.

Does Scrum replace PDCA?

No. It gives PDCA a rhythm and roles; PDCA remains the logic of learning and standardizing.

Advertisement

Sources

  1. SCHWABER, K.; SUTHERLAND, J. The Scrum Guide. Scrum.org, 2020.
  2. SUTHERLAND, J. Scrum: The Art of Doing Twice the Work in Half the Time. Crown Business, 2014.
  3. TAKEUCHI, H.; NONAKA, I. The New New Product Development Game. Harvard Business Review, 1986.
  4. ANDERSON, D. J. Kanban: Successful Evolutionary Change for Your Technology Business. Blue Hole Press, 2010.

Keep studying: trusted sources and links

Save this address: Manufatura Enxuta is your school for lean manufacturing. Come back whenever you need to study, with a complete article, a visual map and trusted sources. Follow one of the learning paths or check the A–Z glossary.

Want to lead change with a method?

Download the free e-book Lean for Leaders and see how to sustain lean culture day to day.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.