Project team building a deliverables tree with cards on a board beside a manufacturing cell being installed.

What is a work breakdown structure

A work breakdown structure (WBS) divides the project scope into smaller and smaller deliverables, in tree form, down to work packages. It answers one question: what must be delivered for the project to be complete?

The WBS describes the what, not the when. It is the base for estimating hours and cost, assigning owners and building the Gantt chart. Without a WBS, the schedule is born with forgotten tasks.

WBS visual map

The map shows the 3-level tree of the example, with its work packages and the total of 440 hours.

WORK BREAKDOWN STRUCTURE
Visual map 137: Work Breakdown Structure (WBS): How to Build One, With Example. Click the map to see it full size.Download the map as PNG
Advertisement

The rules of a good WBS

How to build a WBS in 5 steps

  1. Write the final deliverable at the top (level 1).
  2. Split it into 4 to 7 major deliverables (level 2), by phase or by product component.
  3. Go down to the work packages (level 3), stopping when you can estimate and assign.
  4. Check the 100% rule top-down and bottom-up.
  5. Write the WBS dictionary: for each package, scope, owner, acceptance criteria and estimate.
Advertisement

Worked example: implementing a manufacturing cell

Fictional example. Level 1 is the final deliverable; level 2 has 5 deliverables; level 3 has 10 work packages with hour estimates.

CodeDeliverable / work packageHours% of total
1.1Project management409.1%
1.1.1Project plan and schedule16
1.1.2Progress reports and meetings24
1.2Engineering7216.4%
1.2.1Cell layout40
1.2.2Machine technical specification32
1.3Infrastructure16838.2%
1.3.1Floor and foundations120
1.3.2Electrical and compressed-air network48
1.4Equipment10423.6%
1.4.1Machine receiving and inspection24
1.4.2Installation and leveling80
1.5People and start-up5612.7%
1.5.1Operator training36
1.5.2Testing and acceptance20
1Manufacturing cell implemented440100%

Check: 16 + 24 = 40; 40 + 32 = 72; 120 + 48 = 168; 24 + 80 = 104; 36 + 20 = 56. Total: 40 + 72 + 168 + 104 + 56 = 440 hours, or 100%. Infrastructure carries 38.2% of the work, so that is where the estimate deserves the most attention.

Next, each package becomes tasks with durations and dependencies. Use PERT/CPM to compute the duration, FMEA to deal with what could go wrong in each deliverable, and 5W2H to link actions to owners.

Where a WBS helps on the shop floor

Common mistakes

Frequently asked questions

What is a WBS?

The hierarchical decomposition of project scope into deliverables and work packages. WBS stands for work breakdown structure.

What is the difference between a WBS and a schedule?

The WBS defines what will be delivered; the schedule defines when and in what order. The WBS comes first.

What is the 100% rule?

Child items must add up to all the work of the parent. In the example, the 5 groups add up to the 440 hours.

How many levels should a WBS have?

As many as needed to estimate and assign an owner. For small manufacturing projects, 3 levels are usually enough.

What is a work package?

The lowest level of the WBS: a deliverable with an owner, an hour and cost estimate and acceptance criteria.

What is the WBS dictionary for?

To describe each package (scope, owner, acceptance, estimate) and avoid different interpretations.

Advertisement

Sources

  1. PMI. Practice Standard for Work Breakdown Structures. Project Management Institute.
  2. PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide). Project Management Institute.
  3. KERZNER, H. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley.

Keep studying: trusted sources and links

Save this address: Manufatura Enxuta is your school for lean manufacturing. Come back whenever you need to study, with a complete article, a visual map and trusted sources. Follow one of the learning paths or check the A–Z glossary.

Want the tools ready to use?

Download the free "Problem Solving Kit" e-book, with PDCA, A3, 5 Whys and Ishikawa.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.