A flow of parts entering and leaving an area, with a triangle of three values linking WIP, throughput and lead time

Quick answer: Little's Law says that, in a stable system, the average WIP equals the average throughput multiplied by the average lead time (WIP = throughput × lead time). With it, you calculate one of the three quantities from the other two and understand why reducing work in process reduces flow time.

Advertisement

Little's Law formula

L = λ × W

In factory language: WIP = throughput × lead time. The three sides of the triangle are WIP, throughput and lead time.

The formula is attributed to John D. C. Little, who published the proof in 1961 (you should verify the exact reference at the end of the article). Its value lies in its generality: it holds for any stable system, whether a line, a warehouse, an order queue or a hospital, without depending on how the times vary.

The three ways to use it

I want to calculateFormulaWhen I use it
WIP (L)L = λ × WEstimate how much work in process I have or will have
Lead time (W)W = L ÷ λFind the flow time without timing each part
Throughput (λ)λ = L ÷ WEstimate output from the WIP and the flow time

Always use consistent units: if throughput is in parts per hour, lead time must be in hours, and the WIP comes out in parts.

Example 1: calculating the WIP

Fictional example. A line produces 30 parts per hour and each part takes, on average, 5 hours to go from start to finish.

WIP = 30 parts/h × 5 h = 150 parts

If, when counting the floor, you find well over 150 parts, the line has excess work in process, or the real throughput is lower than assumed.

Example 2: calculating lead time without timing

Fictional example. A cell has on average 480 parts in process and delivers 60 parts per hour.

Lead time = WIP ÷ throughput = 480 ÷ 60 = 8 hours

If the WIP is reduced to 240 parts and throughput holds at 60 per hour:

Lead time = 240 ÷ 60 = 4 hours

Cutting the WIP in half cut the lead time in half, at the same throughput. That is why Little's Law supports the idea that less work in process means shorter flow time. For throughput to hold, you must eliminate the causes of waiting, not just remove parts.

Example 3: limiting WIP with kanban

Fictional example. You want an average lead time of 2 hours on a line that produces 50 parts per hour.

Maximum WIP = 50 parts/h × 2 h = 100 parts

If each kanban container holds 25 parts, the maximum number of containers in the system is 100 ÷ 25 = 4. This is the reasoning behind the WIP limit and the sizing of kanban.

What Little's Law reveals

ObservationReading
Lead time grows when WIP grows, with throughput constantExcess work in process becomes waiting, not production
Increasing WIP does not increase throughput beyond a certain pointThe system's constraint (the bottleneck) limits throughput
To reduce lead time, reduce WIP or increase throughputBoth actions attack the same triangle
Large batches raise the WIPSee transfer batch and production batch to reduce flow time

The bottleneck and queues appear in detail in queueing theory. Little's Law is the most general relation among the three quantities.

Conditions for using the law

Advertisement

How to apply it in your factory

  1. Define the boundary: where the flow you want to analyze starts and ends.
  2. Measure the average throughput for the period, for example parts completed per hour.
  3. Count the WIP at several moments and calculate the average.
  4. Calculate the lead time with the law and compare it with what production perceives.
  5. Look for where the WIP accumulates and attack the causes, such as large batches, waiting and breakdowns (VSM).
  6. Set a WIP limit and track lead time and throughput after the change.

Example 4: open orders in production planning

Fictional example. Production planning has on average 120 open production orders and completes 15 orders per working day.

Average order lead time = 120 orders ÷ 15 orders/day = 8 days

If the goal is a 5-day lead time with the same capacity, the number of open orders must fall to 15 × 5 = 75. The law also holds for administrative queues, such as orders, tickets and purchase requests.

Exercises to practice

  1. A line has 200 parts in process and throughput of 25 parts per hour. What is the average lead time?
  2. A cell delivers 12 parts per hour and the average flow time is 3 hours. What is the average WIP?
  3. A warehouse receives 40 pallets per day and each pallet stays 5 days. How many pallets are in the warehouse, on average?
  4. An area wants a lead time of 4 hours with throughput of 45 parts per hour. What is the maximum WIP?

Answers: (1) 200 ÷ 25 = 8 hours. (2) 12 × 3 = 36 parts. (3) 40 × 5 = 200 pallets. (4) 45 × 4 = 180 parts.

Little's Law and the bottleneck

In a line, the throughput of the system is limited by the bottleneck. If you fill the system with parts beyond what the bottleneck processes, the WIP rises, the lead time rises and throughput does not. That is what the law shows: with throughput locked at the bottleneck, every extra part in the system only increases the flow time.

That is why the golden rule is to release material at the pace of the bottleneck, not at the speed of the first station. See how in drum-buffer-rope scheduling.

Pitfalls

Frequently asked questions

What does Little's Law say?

In a stable system, the average number of items in the system equals the average arrival rate (or throughput) multiplied by the average time each item stays in it: L = λ × W.

What is the Little's Law formula in production?

WIP = throughput × lead time. It is also written as lead time = WIP ÷ throughput, and throughput = WIP ÷ lead time.

How do you calculate lead time with Little's Law?

Divide the average WIP by the average throughput. For example, 480 parts in process and throughput of 60 parts per hour give a lead time of 8 hours.

Does Little's Law hold for any system?

It holds for stable systems, in terms of long-term averages, regardless of how the times vary. It does not hold as an instantaneous measure while the system is filling up or emptying.

Does reducing WIP always reduce lead time?

If throughput holds, yes. But the WIP must come out through eliminating waits and large batches, not through stopping the flow, which would reduce throughput.

What is the relationship between Little's Law and kanban?

Kanban limits the WIP. By the law, when you fix the WIP and know the throughput, you determine the average lead time, and vice versa. This guides the number of cards.

Sources

  1. LITTLE, J. D. C. A Proof for the Queuing Formula: L = λW. Operations Research, v. 9, n. 3, 1961 (confirm volume and pages).
  2. HOPP, W. J.; SPEARMAN, M. L. Factory Physics. 3rd ed. Long Grove: Waveland Press, 2008 (confirm the edition).
  3. ROTHER, M.; SHOOK, J. Learning to See. Cambridge: Lean Enterprise Institute, 1999.

This article is a teaching guide. The numerical examples are fictional and only show how the calculation works; use your own company's data and criteria. For questions about standards or manuals, consult the official document. See also the learning paths and the A–Z glossary.

Want to reduce your factory's lead time?

Download the free e-book Pull Production and see how to limit WIP with kanban.

Download the e-book
Advertisement
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.