Maintenance storeroom shelves with labeled spare parts organized by criticality.

What spare parts and MRO inventory are

Spare parts are the items kept on hand to replace components that fail in your equipment. MRO (Maintenance, Repair and Operations) is the wider group: spares, maintenance consumables (lubricants, belts, seals, PPE) and tools, everything that keeps the plant running but never ends up in the product.

The central question is how much to stock of each item. Too much ties up capital and ages on the shelf; too little turns a $400 failure into days of downtime. The answer takes two steps: rank criticality first, then set the quantity.

Visual map of spare parts and MRO inventory

The map summarizes the criticality matrix, the policy per class and the worked example from this article.

SPARE PARTS AND MRO INVENTORY
Visual map 250: Spare Parts and MRO Inventory: Criticality and Stock Levels. Click the map to see it full size.Download the map as PNG

Step 1: rank criticality

Criticality is not price and not usage. An $18 sensor can stop an entire line. Use two factors scored 1 to 5 and multiply them:

Criticality = Failure impact × Replenishment lead time

Take impact from failure analysis of the equipment: use the FMEA or the answers from RCM, not the opinion of whoever is in a hurry. With a score from 1 to 25, define three classes:

ClassScorePolicy
Critical15 to 25Risk-based stock: quantity set by failure probability over the lead time and by downtime cost
Intermediate6 to 14Min/max with a reorder point, reviewed yearly
Low1 to 5Replenish on consumption, buy on demand or use consignment
Advertisement

Step 2: set the stocking policy

Criticality decides whether and with what margin you stock; usage decides how much. That is why the top and bottom classes follow different logic:

For low-criticality items with unpredictable usage, consider moving the stock to the supplier through VMI or consignment.

Example: a 55 kW variable frequency drive

Fictional example from a bottling plant. The table shows the criticality of six items:

ItemImpactLead timeScoreClass
55 kW variable frequency drive5525Critical
PLC input card5420Critical
Main conveyor gearbox4416Critical
5/2 pneumatic solenoid valve326Intermediate
M18 inductive sensor313Low
6205 bearing313Low

Now size the drive. Data from history and the supplier:

Expected failures during the lead time:

λ = 1 failure/year × 90 ÷ 365 = 0.2466

With the Poisson distribution, P(X = k) = e−λ × λk ÷ k!. For λ = 0.2466:

Failures in lead time (k)P(X = k)P(X ≤ k)
078.15%78.15%
119.27%97.42%
22.38%99.79%
30.20%99.99%

With a 95% service target, the part must be available for at least 95% of failures. When the total stock (on the shelf plus on order) is S, availability is P(X ≤ S − 1). S = 1 gives 78.15%; S = 2 gives 97.42%. Two drives meet the target.

Checking by cost: each extra unit prevents downtime in P(X = k) of failures, and the yearly gain is that value × 1 failure × $120,000:

UnitProbability avoidedYearly gainHolding costWorth it?
1st78.15%$93,777$3,600Yes
2nd19.27%$23,123$3,600Yes
3rd2.38%$2,851$3,600No

The third unit costs more than it saves. Both criteria point to 2 drives. Before buying, compare alternatives: sharing a unit between sister plants, an express repair contract, or standardizing the rating so the same model fits other machines.

Advertisement

Keeping the inventory alive

The calculation ages. Keep it current with a simple routine:

  1. Link each part to its equipment in the asset bill of materials in the CMMS. Without the link, nobody knows where the part is used.
  2. Charge every issue to a work order. That is how real consumption shows up and the calculation self-corrects.
  3. Review the classification once a year and after any change of equipment, supplier or lead time.
  4. Deal with idle items: a low-criticality part with no movement for 24 months is a candidate for write-off, sale or return. An idle critical part is not excess, it is insurance: keep it, but record the justification.
  5. Run cycle counts on critical items, with accuracy close to 100%. A spare the system says exists and does not is worse than none.

Also track the storeroom fill rate (parts requests served on the first ask) next to MTBF and MTTR: repair time includes waiting for the part. To plan the parts for a planned shutdown, work from the scope bill of materials and pull forward the long-lead items.

Common mistakes

Frequently asked questions

What does MRO stand for?

Maintenance, Repair and Operations: spares, maintenance consumables and tools used to keep operations running, outside the finished product.

How do I decide which parts to stock?

Score failure impact and replenishment lead time from 1 to 5 and multiply. High scores (15 or more) deserve risk-based stock.

How do I size stock for a slow-moving critical item?

Compute expected failures over the lead time (λ) and use Poisson to find the smallest quantity that reaches the service target, then check downtime cost against holding cost.

What does holding spare parts cost?

It adds tied-up capital, space, insurance, handling and obsolescence. Many companies use around 20% a year of item value, but the right number is your own.

Should a critical part idle for years be scrapped?

Not necessarily. If failure is unlikely but devastating and the lead time is long, the stock works as insurance. Review the justification, not only the turnover.

What is the difference between a spare and a consumable?

A spare replaces a failed equipment component. A consumable is used up continuously in operation, like lubricant, filters and PPE.

Advertisement

Sources

  1. SILVER, E. A.; PYKE, D. F.; THOMAS, D. J. Inventory and Production Management in Supply Chains. CRC Press.
  2. MOUBRAY, J. Reliability-centred Maintenance. Butterworth-Heinemann, 1997.
  3. WIREMAN, T. Developing Performance Indicators for Managing Maintenance. Industrial Press.
  4. EN 13306: Maintenance terminology.

Keep studying: trusted sources and links

Save this address: Manufatura Enxuta is your school for lean manufacturing. Come back whenever you need to study, with a complete article, a visual map and trusted sources. Follow one of the learning paths or check the A–Z glossary.

Want to measure what really matters?

Download the free e-book on performance indicators and track the losses in your operation.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.