What aggregate production planning is

Aggregate production planning (also called aggregate planning) sets, for a horizon of 6 to 18 months, how much to produce per period, how many people are needed, how much inventory to carry and how much overtime or subcontracting to use, with products grouped into families. The goal is to meet forecast demand at the lowest total cost without yet going into individual items.

It is the link between the demand forecast and day-to-day scheduling: the aggregate plan fixes resources, and the master production schedule breaks it down by product and week. In practice it is approved in the S&OP process.

Advertisement

Visual map of aggregate planning

The map compares the three strategies using the same six-month example and shows the total cost of each.

AGGREGATE PLANNING
Visual map 191: Aggregate Production Planning: Strategies with Example. Click the map to see it full size.Download the map as PNG

The three classic strategies

With demand changing month to month, there are only four levers: workforce size, overtime, inventory and subcontracting. The strategies combine these levers in different ways.

Ending inventory(t) = Ending inventory(t−1) + Production(t) − Demand(t)

Total cost = labor + hiring/layoff + overtime + inventory + shortage

In the level strategy, monthly output is total demand divided by the number of periods. In chase, the number of workers is the month's demand divided by each worker's productivity.

Worked example: six months, three strategies

Fictional example for a furniture plant, with aggregate demand in units of one product family:

Level: 6,000 ÷ 6 = 1,000 units per month, which needs 10 workers (1 hire). Ending inventory builds to 300, 500, 500, 200, 0 and 0: a total of 1,500 unit-months.

Chase: workers = demand ÷ 100, that is 7, 8, 10, 13, 12 and 10. Starting from 9, that is 2 layoffs in month 1, hires of 1, 2 and 3 people in months 2, 3 and 4, and layoffs of 1 and 2 people in months 5 and 6: 6 hires and 5 layoffs.

Mixed: a fixed crew of 9 workers (900 regular units per month) and overtime in the peak months, within the limit of 180 per month (20% of 900). It needs 600 extra units in total, in months 3 to 6.

MonthDemandLevel: outputLevel: ending inventoryChase: workersMixed: outputMixed: ending inventory
Month 17001,0003007900200
Month 28001,0005008900300
Month 31,0001,000500101,040 (900 + 140)340
Month 41,3001,000200131,080 (900 + 180)120
Month 51,2001,0000121,080 (900 + 180)0
Month 61,0001,0000101,000 (900 + 100)0
Total6,0006,0001,500606,000960

Costs, in dollars:

ItemLevelChaseMixed
Regular labor240,000240,000216,000
Overtime0028,800
Hiring and layoff1,50019,0000
Inventory15,00009,600
Total cost256,500259,000254,400

How it was calculated: regular labor = workers × months × $4,000 (level 10 × 6; chase 60 worker-months; mixed 9 × 6 = 54 worker-months, $216,000). Mixed overtime = 600 × $48 = $28,800. Chase hiring and layoff = 6 × 1,500 + 5 × 2,000 = $19,000. Inventory = unit-months × $10 (level 1,500; mixed 960).

The mixed strategy is the cheapest at $254,400: 0.8% below level and 1.8% below chase. The gap is small, which is typical: the result depends on the cost inputs.

Advertisement

How to build the aggregate plan, step by step

  1. Aggregate demand into a common unit: family units, standard hours or tons. Use the consolidated demand forecast.
  2. Compute capacity per period (workers × productivity × days) and the overtime limit, as in production capacity.
  3. Gather costs: regular and overtime labor, hiring, layoff, inventory per unit-month, shortage or backorder, subcontracting.
  4. Build the plans in a spreadsheet, one per strategy, computing output, inventory and crew each month.
  5. Add up the costs and compare. For many periods and constraints, use linear programming, which finds the lowest-cost combination.
  6. Check feasibility: inventory never negative, overtime within limit, storage space and staffing policy.
  7. Approve it in S&OP and break it down in the master schedule and in MRP.

How to choose a strategy

Test sensitivity: vary inventory, overtime and hiring costs by ±30% and see whether the ranking changes. If it does, the decision is fragile and deserves closer analysis. Non-financial factors such as turnover, quality and morale also count, and the plan must fit the plant's production planning and control structure.

Common mistakes and limitations

Frequently asked questions

What is aggregate planning?

Medium-term planning that sets output, workforce, inventory and overtime per period for product families at the lowest cost.

What are the aggregate planning strategies?

Chase (output follows demand), level (constant output with inventory) and mixed (stable workforce with overtime or subcontracting).

What is the difference between aggregate planning and the master schedule?

Aggregate planning works with families and months; the master schedule works with products and weeks and is the breakdown of the aggregate plan.

Which strategy is best?

It depends on the costs. In the example, mixed cost $254,400 versus $256,500 for level and $259,000 for chase.

How does S&OP relate to the aggregate plan?

S&OP is the monthly process in which sales, operations and finance approve the aggregate plan and resolve gaps between demand and capacity.

What horizon should I use?

Usually 6 to 18 months, reviewed every month, in monthly periods.

Advertisement

Sources

  1. HOLT, C. C.; MODIGLIANI, F.; MUTH, J. F.; SIMON, H. A. Planning Production, Inventories, and Work Force. Englewood Cliffs: Prentice-Hall, 1960.
  2. CHASE, R. B.; JACOBS, F. R.; AQUILANO, N. J. Operations Management for Competitive Advantage. McGraw-Hill.
  3. NAHMIAS, S. Production and Operations Analysis. McGraw-Hill.
  4. HOPP, W. J.; SPEARMAN, M. L. Factory Physics. McGraw-Hill.

Keep studying: trusted sources and links

Save this address: Manufatura Enxuta is your school for lean manufacturing. Come back whenever you need to study, with a complete article, a visual map and trusted sources. Follow one of the learning paths or check the A–Z glossary.

Want a quick reference guide for the factory floor?

Download the free Pocket Guide e-book with the Lean tools summarized on one page each.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.