What value engineering and value analysis are

Value engineering (VE) and value analysis (VA) are one method applied at different moments: VE works on the design before production, VA works on a product already in the line. The method asks which function the item must perform and what the lowest cost is to deliver it, without losing performance or quality.

The starting point is L. D. Miles at General Electric in the 1940s. The core idea: the customer pays for the function, not for the material or the part. That is why the method is not cost cutting: cutting the wrong part lowers value.

Visual map of value engineering

The map shows the value equation, the function-cost matrix and the example from $12.00 down to $9.80.

VALUE ENGINEERING (VA/VE)
Visual map 261: Value Engineering and Value Analysis: Function, Cost, Value. Click the map to see it full size.Download the map as PNG

Value, function and cost

Value = Function (performance) ÷ Cost

There are four ways to raise value: keep the function and cut cost; raise the function at the same cost; raise the function at a lower cost; or raise the function slightly more than the cost. In plant practice the first and third are the most common.

A function is written as a verb + noun: "support load", "seal fluid", "hold part". The rule forces the team to step away from the part and think about what it does. Basic functions (the reason the product exists) are separated from secondary functions (those that support or follow from the chosen design).

Advertisement

The phases of the job plan

  1. Information: collect drawings, costs, volumes and customer requirements. Pick the highest-cost items using the ABC curve logic.
  2. Function analysis: list functions as verb and noun and assign each an importance (%).
  3. Creativity: generate alternatives without judging, as in brainstorming.
  4. Evaluation: screen ideas by technical feasibility, cost and risk.
  5. Development: detail the best ones, test prototypes and calculate the gain with the production cost.
  6. Presentation and implementation: take the proposal with numbers to the decision and track the result.

Example: function-cost matrix of a 5-component assembly

Fictional example: an assembly costs $12.00 per unit. The team gave each component's function an importance percentage (total 100%). The value index is the % of function divided by the % of cost; the target cost is the % of function times the total cost.

Value index = % function ÷ % cost | Target cost = % function × $12.00

ComponentCurrent cost% of cost% of functionValue indexTarget costGap
Housing$4.5037.5%30%0.80$3.60+0.90
Cover$2.0016.7%10%0.60$1.20+0.80
Screws$1.2010.0%15%1.50$1.80-0.60
Gasket$0.806.7%20%3.00$2.40-1.60
Bracket$3.5029.2%25%0.86$3.00+0.50
Total$12.00100%100%$12.00

Housing example: 4.50 ÷ 12.00 = 37.5% of cost; 30 ÷ 37.5 = 0.80; target cost = 0.30 × 12.00 = $3.60; gap of $0.90. An index below 1 means cost above the function delivered. Housing (0.80), cover (0.60) and bracket (0.86) are candidates. Gasket (3.00) and screws (1.50) have a high index: they are not cutting targets and may even deserve more investment.

Advertisement

From value index to savings

The team produced three proposals, each bringing a component to its target cost while keeping the function:

Saving per unit: 0.90 + 0.80 + 0.50 = $2.20. Cost drops from $12.00 to $9.80, a reduction of 18.3% (2.20 ÷ 12.00). At 40,000 units a year: 2.20 × 40,000 = $88,000 per year. Total function (100%) stays, so value moves from 100 ÷ 12.00 = 8.33 to 100 ÷ 9.80 = 10.20 function points per dollar, an increase of 22.4%.

Before implementing, compare tooling and testing spend with this saving using payback and NPV, and validate the stamped cover and the housing with performance tests.

When to use it and how to combine it with other tools

Common mistakes

Frequently asked questions

What is the difference between value engineering and value analysis?

It is the same method. Value engineering is applied during design; value analysis on products already in production.

What is the value formula?

Value = function (performance) ÷ cost. To raise value, keep or raise the function and lower the cost.

How do you calculate the value index?

Divide the function importance percentage by the component cost percentage. For the housing: 30 ÷ 37.5 = 0.80.

What is target cost in value analysis?

The cost the component would have if it followed its functional importance: % function × total cost. For the housing: 0.30 × 12.00 = $3.60.

Is value engineering the same as cost reduction?

No. The goal is to keep or raise the function at lower cost. Cuts that degrade the function lower the value.

Who should join the study?

A cross-functional team: design, production, quality, purchasing and, when possible, the customer or someone who knows the requirements.

Advertisement

Sources

  1. MILES, L. D. Techniques of Value Analysis and Engineering. New York: McGraw-Hill, 1961.
  2. EN 12973. Value Management.
  3. SAVE International. Value Methodology Standard.
  4. MUDGE, A. E. Value Engineering: A Systematic Approach. New York: McGraw-Hill, 1971.

Keep studying: trusted sources and links

Save this address: Manufatura Enxuta is your school for lean manufacturing. Come back whenever you need to study, with a complete article, a visual map and trusted sources. Follow one of the learning paths or check the A–Z glossary.

Want to measure what really matters?

Download the free e-book on performance indicators and track the losses in your operation.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.