Problem prioritization board in a plant management meeting, with cards ordered from most to least critical.

What is a GUT matrix

A GUT matrix is a prioritization tool that scores each problem for Gravity (severity), Urgency and Tendency (growth) from 1 to 5 and multiplies the three. The product, from 1 to 125, builds the ranking: the highest score gets tackled first.

It is usually credited to Charles Kepner and Benjamin Tregoe and works when there are more problems than people and time to solve them. On the shop floor it is the fastest way to turn a list of complaints into an order of attack the team can defend.

GUT matrix visual map

The map shows the scoring scale, the G × U × T formula and the ranking of the worked example in this article.

GUT MATRIX
Visual map 130: GUT Matrix Prioritization: Scoring, Example and Template. Click the map to see it full size.Download the map as PNG
Advertisement

Formula and scoring scale

GUT score = Gravity × Urgency × Tendency

ScoreGravityUrgencyTendency
1No gravityCan waitWill not get worse
2Slightly seriousLow urgencyGets worse in the long term
3SeriousAs soon as possibleGets worse in the medium term
4Very seriousUrgentGets worse shortly
5Extremely seriousImmediate actionGets worse quickly

Because the calculation is a product, a 1 in any dimension drags the score down. A problem can be severe (G = 5), but if urgency and tendency are 1 it scores 5 and goes to the end of the queue.

Worked example: plastic packaging plant

Fictional example. The team at a packaging plant listed six problems and, in a meeting with production, quality and maintenance, agreed on these scores:

RankProblemGUTG × U × T
1Customer complaint about damaged packaging5455 × 4 × 5 = 100
2Unplanned stops on injection machine 35445 × 4 × 4 = 80
3Late raw-material deliveries4354 × 3 × 5 = 60
4Scrap at finishing4434 × 4 × 3 = 48
5Tools out of place during mold changeover2332 × 3 × 3 = 18
6Poor lighting in the shipping area2222 × 2 × 2 = 8

The scores add up to 100 + 80 + 60 + 48 + 18 + 8 = 314. The top three total 240, or 76% of the sum. That is where the team focuses its action plan.

RankProblemPointsCumulative %
1Customer complaint about damaged packaging10032%
2Unplanned stops on injection machine 38057%
3Late raw-material deliveries6076%
4Scrap at finishing4892%
5Tools out of place during mold changeover1897%
6Poor lighting in the shipping area8100%

Note that the customer complaint (5 × 4 × 5) ranks above the injection machine stops (5 × 4 × 4) only because of tendency: an unhappy customer gets worse quickly, while the machine problem develops more slowly.

Advertisement

How to build the matrix in 5 steps

  1. List the problems as concrete statements, without a solution built in. Use the gemba, the metrics and customer complaints; see the area's visual management boards.
  2. Define the scale and write down what each score from 1 to 5 means before scoring, so everyone uses the same ruler.
  3. Score as a group, with people who know the process. Everyone proposes a score and differences are discussed, not averaged blindly.
  4. Multiply and sort from the highest product to the lowest.
  5. Turn the top into action: for the first items, build a 5W2H action plan or an A3 report, and revisit the matrix when the situation changes.

GUT, Pareto and FMEA: when to use each

The Pareto chart ranks by measured data (defect counts, downtime minutes, cost). GUT ranks by team judgment and fits when reliable data does not exist yet, when problems are of different natures (safety, delivery, quality) or when a quick decision is needed. The best approach is to combine them: Pareto where there is data, GUT to compare items that do not fit on the same chart. For process or product risks scored on severity, occurrence and detection, the right tool is FMEA. For the other basic tools, see the 7 quality tools.

Common mistakes and limitations

Frequently asked questions

What does GUT stand for?

Gravity, Urgency and Tendency: the three dimensions used to score each problem.

How do you calculate a GUT matrix?

Give G, U and T a score from 1 to 5 and multiply them. The result runs from 1 to 125; the higher, the higher the priority.

What is the difference between gravity, urgency and tendency?

Gravity is the size of the damage, urgency is the time before it happens, and tendency is how the problem evolves if nothing is done.

Does the GUT matrix replace Pareto analysis?

No. Pareto uses measured data; GUT uses team judgment. They complement each other.

How many problems fit in a GUT matrix?

Usually 5 to 15. Beyond that, group similar problems or split by area before scoring.

Who should do the scoring?

A small group that knows the problem first-hand: operations, quality, maintenance and the area leader.

Advertisement

Sources

  1. KEPNER, C. H.; TREGOE, B. B. The Rational Manager. New York: McGraw-Hill, 1965.
  2. SLACK, N.; BRANDON-JONES, A.; JOHNSTON, R. Operations Management. Pearson.
  3. TAGUE, N. R. The Quality Toolbox. Milwaukee: ASQ Quality Press.

Want the tools ready to use?

Download the free "Problem Solving Kit" e-book, with PDCA, A3, 5 Whys and Ishikawa.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.