A project manager points at a printed S-curve chart pinned to the wall of a project room next to the factory floor.

What earned value management (EVM) is

Earned value management (EVM) measures project schedule and cost on the same scale: money. It compares what was planned, what was actually accomplished (in value) and what was spent, and produces indexes that show whether the project is ahead or behind schedule, over or under budget.

The S curve is the cumulative plot of those values over time. The “S” shape comes from the typical pace: slow start, fast middle, slow finish.

Advertisement

Visual map: PV, EV, AC, CPI and SPI

The map gathers the three base values, the variance and index formulas, the $100,000 example and the forecasts.

EARNED VALUE (EVM)
Visual map 231: Earned Value Management and S-Curve: Control Cost and Schedule. Click the map to see it full size.Download the map as PNG

The three base values

To spread PV by deliverable, start from a good work breakdown structure (WBS): each work package gets a budget and a planned date.

Variances and indexes

CV = EV − AC  |  SV = EV − PV  |  CPI = EV ÷ AC  |  SPI = EV ÷ PV

MeasureFormulaReading
CV (cost variance)EV − ACNegative: spent more than the value delivered
SV (schedule variance)EV − PVNegative: delivered less than planned
CPI (cost performance index)EV ÷ ACBelow 1: cost above plan
SPI (schedule performance index)EV ÷ PVBelow 1: pace below plan

Worked example: a $100,000 project

Fictional example: a 6-month project with a BAC of $100,000. The table shows the cumulative figures through month 3, the status date.

MonthCum. PV ($)Cum. EV ($)Cum. AC ($)CPISPI
110,0008,00012,0000.6670.800
225,00022,00028,0000.7860.880
340,00035,00042,0000.8330.875

The planned PV for the remaining months is 65,000 (month 4), 85,000 (month 5) and 100,000 (month 6). At month 3:

On the S curve, the three cumulative lines are in this order at month 3: AC (42,000) on top, PV (40,000) in the middle and EV (35,000) at the bottom. That is the classic picture of a project that is late and over budget.

Advertisement

Forecasts: what it will cost at the end

EAC = BAC ÷ CPI  |  ETC = EAC − AC  |  VAC = BAC − EAC  |  TCPI = (BAC − EV) ÷ (BAC − AC)

ForecastAssumptionCalculationResult
EAC (cost trend)Current performance continues100,000 ÷ 0.833$120,000
ETC (estimate to complete)Same assumption120,000 − 42,000$78,000
VAC (variance at completion)Same assumption100,000 − 120,000−$20,000
EAC (one-off variance)The overrun was a one-time event, the rest follows plan42,000 + (100,000 − 35,000)$107,000
EAC (cost and schedule)Cost and schedule weigh together42,000 + 65,000 ÷ (0.833 × 0.875)$131,143
TCPI (to finish at BAC)Finish within budget(100,000 − 35,000) ÷ (100,000 − 42,000)1.121

A TCPI of 1.121 says that from now on every $1.00 spent would have to return $1.12 of value. If the team has been returning $0.83, that target is unrealistic, and the conversation becomes about asking for more budget or cutting scope. Choose the EAC formula by the cause of the variance, not by the most optimistic one.

Reading CPI and SPI together

CPISPISituation
Above 1Above 1Ahead of schedule and under cost
Above 1Below 1Behind schedule, but spending less than the value delivered
Below 1Above 1Ahead of schedule, but over cost
Below 1Below 1Behind schedule and over cost (the example)

Set action thresholds beforehand, for example investigate below 0.90 and escalate below 0.80. The numbers belong to the company, not to theory. To understand a delay, cross the SPI with the critical path: a low SPI on an activity with float may be harmless; on a critical activity, it is not.

How to measure EV for each work package

To plan for uncertainty in durations and costs before you start, see Monte Carlo simulation and the risk matrix.

Common mistakes and limitations

In construction, the logic of short planning cycles with reliable promises appears in the Last Planner System; in plant costing, variance analysis is a relative of standard costing and variances.

Frequently asked questions

What is EVM?

A method that integrates scope, schedule and cost by comparing planned value (PV), earned value (EV) and actual cost (AC).

What is the S curve?

The cumulative plot of PV, EV and AC over time; the S shape comes from a slow start, a fast middle and a slow finish.

How do you calculate CPI and SPI?

CPI = EV ÷ AC and SPI = EV ÷ PV. In the example: 35,000 ÷ 42,000 = 0.833 and 35,000 ÷ 40,000 = 0.875.

Is a CPI below 1 bad?

It means cost is above the value delivered. The earlier it appears and the further from 1, the higher the risk of a budget overrun.

How do you calculate the estimate at completion (EAC)?

By trend: EAC = BAC ÷ CPI. In the example, 100,000 ÷ 0.833 = $120,000.

What is the difference between EV and AC?

EV is the budget of the completed work; AC is what was spent to complete it. The difference between them is the cost variance.

Advertisement

Sources

  1. PROJECT MANAGEMENT INSTITUTE. A Guide to the Project Management Body of Knowledge (PMBOK Guide). PMI.
  2. PROJECT MANAGEMENT INSTITUTE. Practice Standard for Earned Value Management. PMI.
  3. FLEMING, Q. W.; KOPPELMAN, J. M. Earned Value Project Management. Project Management Institute.
  4. LIPKE, W. Schedule is Different. The Measurable News, 2003.

Keep studying: trusted sources and links

Save this address: Manufatura Enxuta is your school for lean manufacturing. Come back whenever you need to study, with a complete article, a visual map and trusted sources. Follow one of the learning paths or check the A–Z glossary.

Want to measure what really matters?

Download the free e-book on performance indicators and track the losses in your operation.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.