- What a weighted decision matrix and a Pugh matrix are
- Visual map of the decision matrix
- How to calculate the weighted matrix
- Example: choosing an automatic labeling machine
- Sensitivity test on the weights
- Pugh matrix: comparing against a reference
- When to use each one
- Common mistakes
- Frequently asked questions
What a weighted decision matrix and a Pugh matrix are
A weighted decision matrix compares alternatives against criteria that carry different weights: each option gets a score per criterion, the score is multiplied by the weight, and the sum shows the best choice. A Pugh matrix does the same comparison in a simpler way, rating each option against a reference with +, 0 and − signs.
Use both when a decision involves several criteria beyond price: buying a machine, picking a supplier, selecting a layout or software. They do not replace judgment, but they force the team to state what matters and how much.
Visual map of the decision matrix
The map shows criteria, weights, scores and the total per alternative, using the same example worked below.

How to calculate the weighted matrix
Option total = Σ (criterion weight × option score on that criterion)
Step by step:
- List 4 to 8 criteria that really separate the options. A criterion all options meet equally does not belong.
- Assign weights that add up to 100 (or 1.00). Weight expresses importance and is set before looking at the scores.
- Define the scoring scale (for example, 1 to 5) and what each score means for each criterion.
- Score every option on every criterion, preferably with data: quotes, datasheets, site visits, customer references.
- Multiply, add, and divide by 100 to get the weighted average score.
Example: choosing an automatic labeling machine
Fictional example: a plant must choose among three labelers (A, B and C). The team set five criteria with weights adding to 100 and scores from 1 (poor) to 5 (excellent).
| Criterion | Weight | Score A | Score B | Score C |
|---|---|---|---|---|
| Total cost of ownership | 30 | 4 | 3 | 5 |
| Quality and accuracy | 25 | 3 | 5 | 3 |
| Delivery and installation lead time | 15 | 5 | 3 | 2 |
| Local technical support | 15 | 3 | 4 | 2 |
| Ease of operation | 15 | 4 | 3 | 5 |
| Sum of weights | 100 |
Each score is multiplied by the criterion weight:
| Criterion | Score A | Score B | Score C |
|---|---|---|---|
| Total cost of ownership (30) | 30 × 4 = 120 | 30 × 3 = 90 | 30 × 5 = 150 |
| Quality and accuracy (25) | 25 × 3 = 75 | 25 × 5 = 125 | 25 × 3 = 75 |
| Delivery and installation lead time (15) | 15 × 5 = 75 | 15 × 3 = 45 | 15 × 2 = 30 |
| Local technical support (15) | 15 × 3 = 45 | 15 × 4 = 60 | 15 × 2 = 30 |
| Ease of operation (15) | 15 × 4 = 60 | 15 × 3 = 45 | 15 × 5 = 75 |
| Weighted total (average score) | 375 (3.75) | 365 (3.65) | 360 (3.60) |
Option A wins with 375 points (average 3.75), ahead of B (365) and C (360). The gap is small, and that is information in itself: the decision is sensitive to the weights and deserves the test in the next section.
Sensitivity test on the weights
Weights are opinions. Before closing, change them within a reasonable range and check whether the winner changes. If finance pushes and cost goes from 30 to 40, with quality at 20 and lead time at 10, the result flips:
| Weight scenario | A | B | C |
|---|---|---|---|
| Base: cost 30, quality 25, lead time 15, support 15, operation 15 | 375 | 365 | 360 |
| Test: cost 40, quality 20, lead time 10, support 15, operation 15 | 375 | 355 | 385 |
With cost at 40, option C moves to first place (385 points). When a plausible change flips the ranking, the choice is not robust: revisit the weights with the decision makers, get better data for the most uncertain scores, or deepen the cost criterion with a total cost of ownership analysis instead of using only the purchase price.
Pugh matrix: comparing against a reference
Stuart Pugh, a professor of engineering design, proposed the method for concept selection in early phases, when there is not enough data for numeric scores. You pick a reference option (the datum, usually the current solution or the best known one) and compare each competitor criterion by criterion: + if better, 0 if equivalent, − if worse.
In the same example, using B as the datum:
| Criterion | Weight | A vs. B | C vs. B | A (weight) | C (weight) |
|---|---|---|---|---|---|
| Total cost of ownership | 30 | + | + | +30 | +30 |
| Quality and accuracy | 25 | − | − | −25 | −25 |
| Delivery and installation lead time | 15 | + | − | +15 | −15 |
| Local technical support | 15 | − | − | −15 | −15 |
| Ease of operation | 15 | + | + | +15 | +15 |
| Result | +3 / −2 = +1 | +2 / −3 = −1 | +20 | −10 |
A has three better and two worse criteria than B (net +1). C has two better and three worse (net −1). Weighting the signs gives A +20 and C −10: A beats the reference, C does not.
Pugh's strength is speed and focus: it shows where each option loses, and those weaknesses can become improvement ideas. The usual practice is to drop the worst options, combine the best features of the leaders, and run another round with a new datum.
When to use each one
- Weighted matrix: purchase or sourcing decisions where data exists and the choice must be documented.
- Pugh: concept phase, many ideas and little information; a filter to cut 8 options to 3.
- Ranking problems: to order problems rather than choose between exclusive options, the GUT matrix fits better.
- Decisions under uncertainty with probabilities: use a decision tree and expected monetary value.
- Focus on function and cost: value engineering measures the value index of each solution.
To generate the options and criteria, brainstorming with an affinity diagram helps collect and group ideas before the matrix. To compare the risks of each option, see the project risk register.
Common mistakes
- Setting weights after seeing the scores. The group tunes the weight so the favorite wins. Freeze the weights first.
- Overlapping criteria. Delivery lead time and installation lead time, for instance, count the same factor twice.
- Scores without objective definitions. Without defining what 1, 3 and 5 mean, everyone uses a different ruler.
- Treating the total as truth. 375 against 365 is a practical tie. Small gaps call for a sensitivity test.
- Ignoring knockout criteria. Legal or safety requirements are pass/fail and must be screened before scoring.
- A single decision maker. The matrix is worth more when operations, maintenance, quality and finance score together.
Frequently asked questions
What is a weighted decision matrix?
A table that compares options against criteria with different weights. Each score is multiplied by its criterion weight, and the sum shows the best option.
What is the difference between a decision matrix and a Pugh matrix?
The weighted matrix uses numeric scores and weights. The Pugh matrix compares each option with a reference using +, 0 and −, and is faster for early phases.
How many criteria should I use?
Between 4 and 8. Fewer makes the decision thin; more dilutes the weights and makes discussion harder.
How do I set the criteria weights?
As a group, before scoring, by distributing 100 points among the criteria. For more rigor, compare the criteria pairwise.
Why does A win in the example?
A totals 375 against 365 for B and 360 for C. If cost rises to a weight of 40, C wins with 385, which is why sensitivity testing is part of the method.
Is a weighted decision matrix the same as a weighted scoring model?
Yes. Weighted scoring model, decision matrix and multi-criteria scoring all describe the same weights-times-scores calculation.
Sources
- PUGH, S. Total Design: Integrated Methods for Successful Product Engineering. Addison-Wesley, 1991.
- PUGH, S. Creating Innovative Products Using Total Design. Addison-Wesley, 1996.
- SLACK, N.; BRANDON-JONES, A.; JOHNSTON, R. Operations Management. Pearson.
- PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide). Project Management Institute.
Keep studying: trusted sources and links
- ABEPRO: Associação Brasileira de Engenharia de Produção (in Portuguese)
- PMI: Project Management Institute
- Wikipedia: Decision matrix
Save this address: Manufatura Enxuta is your school for lean manufacturing. Come back whenever you need to study, with a complete article, a visual map and trusted sources. Follow one of the learning paths or check the A–Z glossary.
Want the tools ready to use?
Download the free "Problem Solving Kit" e-book, with PDCA, A3, 5 Whys and Ishikawa.
Download the e-book