Project lead and colleagues placing magnets on a two-by-two grid on a whiteboard beside a machining cell

What stakeholder analysis is

Stakeholder analysis identifies who is affected by a project or can affect it, rates each person's power and interest, and decides how to engage them. The power-interest grid is the most common tool: it crosses the two axes into four quadrants, each with its own communication strategy.

On the shop floor, projects rarely fail for technical reasons. They fail because the shift supervisor was not heard, the director found out late or maintenance had no time to take part. The grid makes visible who needs attention before the problem shows up.

Visual map: quadrants and engagement strategy

The map shows the four quadrants, the scoring scale and the classification of the eight stakeholders in the example.

POWER-INTEREST GRID
Visual map 293: Stakeholder Analysis: Power Interest Grid with Example. Click the map to see it full size.Download the map as PNG
Advertisement

How to build the grid in 5 steps

  1. List: everyone affected or influential, by name or role. Start from the project charter and the work breakdown structure: who performs, approves, supplies and receives each deliverable.
  2. Score power (1 to 10): ability to approve, block, release resources or stop production.
  3. Score interest (1 to 10): how much the project changes the person's routine, results or career.
  4. Classify: a score of 6 or more is high; below 6 is low. This cut-off is a convention of the example; set yours and keep it.
  5. Define the action: who, what, when and how often, in a 5W2H action plan.

The four quadrants

QuadrantPowerInterestStrategy
Manage closelyHighHighInvolve in decisions, frequent meetings, listen before deciding
Keep satisfiedHighLowReport results and risks briefly, without overloading
Keep informedLowHighClear communication and a feedback channel; many become multipliers
MonitorLowLowMinimum effort, review if the situation changes

Example: machining cell layout reorganization

Fictional example. Eight stakeholders, scores from 1 to 10, high = 6 or more. The priority index is power × interest and orders people within a quadrant.

StakeholderPowerInterestPower × InterestQuadrantCurrent stance
Plant director9545Keep satisfiedNeutral
Production manager8972Manage closelySupportive
Maintenance lead6848Manage closelyNeutral
Shift supervisors5945Keep informedResistant
Cell operators3927Keep informedApprehensive
Quality engineering4728Keep informedSupportive
Purchasing4312MonitorNeutral
Part customer (auditor)7321Keep satisfiedNeutral

Priority index = power × interest (e.g., production manager 8 × 9 = 72)

Result: 2 stakeholders in "manage closely" (production manager, 72, and maintenance lead, 48), 2 in "keep satisfied", 3 in "keep informed" and 1 in "monitor". All 8 are accounted for (2 + 2 + 3 + 1).

Advertisement

From quadrant to engagement plan

The grid only pays off when the current stance is compared with the desired one. In the example, shift supervisors have interest 9 and power 5, and are resistant: the layout changes their routine. They sit in "keep informed", but the risk calls for a more demanding approach. Suggested action:

For the behavioral side of change, see ADKAR and Kotter's 8 steps. Risks that come from people go into the risk matrix, and the organizational context can be mapped with a SWOT analysis.

When and how often to update

Common mistakes

Frequently asked questions

What is the power-interest grid?

A two-axis chart that places each stakeholder in one of four quadrants and sets the engagement strategy for each.

Who are the stakeholders in a manufacturing project?

Anyone affected by or able to affect the project: management, production, maintenance, quality, operators, purchasing, customers, suppliers and regulators.

What is the difference between a stakeholder and a customer?

The customer is one type of stakeholder. Stakeholders also include the team, managers, suppliers and the community.

How do you classify someone with high power and low interest?

In 'keep satisfied': report results and risks briefly and regularly, without requiring involvement in the detail.

How often should the analysis be updated?

At every project milestone and whenever people, scope or priorities change.

Is the power-interest grid the only method?

No. There are also the power-influence grid and the salience model, but power-interest is the simplest place to start.

Advertisement

Sources

  1. FREEMAN, R. E. Strategic Management: A Stakeholder Approach. Boston: Pitman, 1984.
  2. MENDELOW, A. L. Stakeholder mapping. Proceedings of the Second International Conference on Information Systems, Cambridge, MA, 1991.
  3. EDEN, C.; ACKERMANN, F. Making Strategy: The Journey of Strategic Management. London: Sage, 1998.
  4. PROJECT MANAGEMENT INSTITUTE. A Guide to the Project Management Body of Knowledge (PMBOK Guide), stakeholder management.
  5. ISO 9001:2015. Quality management systems, requirements, clause 4.2 (interested parties).

Keep studying: trusted sources and links

Save this address: Manufatura Enxuta is your school for lean manufacturing. Come back whenever you need to study, with a complete article, a visual map and trusted sources. Follow one of the learning paths or check the A–Z glossary.

Want to lead change with a method?

Download the free e-book Lean for Leaders and see how to sustain lean culture day to day.

Download the e-book
Photo of Vagner Soares

About the author

Vagner Soares

Lean Manufacturing & Behavioral Management Specialist

Over 20 years in the automotive and metalworking industries (GM and Dana), Lean Manufacturing practitioner since 2006. SENAI instructor and mentor in Brazil’s Brasil Mais Produtivo program, delivering consulting, training and audits for 50+ companies, combining quality, productivity and people development.